On a sloping plot, the yard ends up with steps, a retaining wall and a terrace at house level. The Urban Planning Code (Legea 169/2026) does not treat them as a building but as landscaping works, and puts them on a short list of works that can be done with no formality at all. The list is on the page about works without a permit, as an enumeration. Here I read what it says word by word, because each word in it can take a work off the list.
What article 299 says exactly
Article 299 para. (2) lit. b) point 4 exempts retaining walls or access steps at ground floor, inside the property, demountable outdoor terraces and pergolas inside the property, outside protected built-up zones. Four conditions can be read out of the sentence:
- Steps at ground floor. The text speaks of access steps at ground floor; read plainly, it does not cover a stair to an upper floor.
- Inside the property. A wall standing on the boundary, not in your yard, is not covered by the text. Where the boundary is and how a shared divider is split with the neighbour is in the fence: permit, height and the neighbour.
- Terraces that are demountable. A poured terrace with a foundation is not on the list. On the demountable terrace and the pergola as outbuildings, see outbuildings: maximum area and papers.
- Outside protected built-up zones. The condition sits at the end of the sentence. Grammatically it could apply only to the last item, but article 294 para. (4) lit. h) treats the same three works within protected built-up zones, by notification. The coherent reading is that the article 299 exception applies outside them.
A retaining wall is on the list with no height limit. The text sets none.
The set-back from the street or a neighbour is a separate matter. Annex 1 lifts the non aedificandi ban for fences, accesses and low terraces, not for retaining walls. If the wall would fall inside the set-back, check the local regulation, because article 299 para. (3) keeps the duty to respect urban planning rules. On set-backs, see the fence: permit, height and the neighbour.
The 3 metres are not an exemption threshold
The 3 m figure appears in another article. Article 289 para. (2) lit. b) lists the supporting documentation required for a permit for landscaping works and says they may include a geotechnical expertise, among other cases if the landscaping involves retaining walls higher than 3 m. That is a file rule for works that need a permit, described in geotechnical study or expertise.
It does not follow that a 2.9 m wall is built with no formality and a 3.1 m one needs a permit. The article 299 exemption has no threshold. What stays standing is paragraph (3) of the same article: a work done with no formality must respect urban planning rules, the technical rules on building quality and the environmental and heritage legislation, and responsibility lies with the beneficiary, jointly with the designers and builders (para. (4)). A tall wall on a slope at risk of sliding does not get simpler because the article exempts it from a permit.
Repair and replacement have their own regime
If the wall, steps or terrace already exist, the list in article 299 para. (2) lit. a) has another point, number 6: repair, replacement or rehabilitation works, without changing the quality and architectural form of the façade elements, to pavements or access steps and outdoor terraces, again outside protected built-up zones and the protection zones of monuments.
Two things are not visible from its title:
- Retaining walls are not on this point. For protection zones and protected zones, their repair appears, next to fences, in two places: on the notification list (art. 294 para. (3) lit. f)) and among the works that can be done without a permit (art. 284 para. (3) lit. f)), two texts that do not line up. For a wall outside those zones the text does not answer directly, so ask the council which regime applies.
- For the works under point 6, the participation of an architect with the right to sign is mandatory (art. 264 para. (8)). No permit does not mean no signed design.
In a protected zone: notification
Article 294 para. (4) lists the landscaping works carried out on notification to the local authorities. Letter h) covers pavements, retaining walls or access steps, outdoor terraces within protected built-up zones, on condition that the Ministry of Culture is notified. So, in a protected built-up zone, a work exempt outside it becomes a work on notification, with a second notification, to the ministry. The steps of a notification are on the page about the simplified notification. It comes with an execution technical design of simplified content, drawn up with the participation of an architect with the right to sign (art. 295 para. (4), art. 264 para. (8)). Work starts only after the terms in article 296 have run (art. 298 para. (1)), is done without technical verification and with an investment identification board in a visible place (art. 298 para. (2) and (5)).
Letter h) speaks only of protected built-up zones, not of the protection zone of a monument. If your plot is in the latter, the information-only urbanism certificate tells you which regime applies; for the context of a house, see a house in a monument’s protection zone.
No formality does not mean no completion acceptance
Article 299 para. (5) requires completion acceptance for works done with no formality as well. It is carried out under the contract between beneficiary and builder and is entered, together with the execution design, in the building’s technical book and in the National Register of Constructions. On the register, see the National Register of Constructions, in brief.
What is left with the permit
Anything not on the list starts from the rule in article 259 para. (6): a building permit is mandatory, with the exceptions of notification and of no formalities. Read plainly, a stair to an upper floor, a poured terrace with a foundation or a wall on the boundary need a permit if they fit no other exception; if in doubt, ask the council in writing. The fee and the file steps are on the page about the building permit; for larger landscaping, on the landscaping permit.
The order in which to check
- Is the work inside your own plot, outside protected built-up zones? Then, on a plain reading of the text, a retaining wall, ground-floor steps or a demountable terrace need neither a permit nor a notification.
- Is it a repair or replacement of existing steps or a terrace? Do not change the façade’s form and involve an architect with the right to sign.
- Is it a protected built-up zone? Notification to the council and to the Ministry of Culture, with a simplified design by an architect and an identification board.
- Is the wall tall or the ground sliding? Paragraph (3) requires the technical rules even without a permit, so settle with your designer whether you need a geotechnical study.
- Do you fit none of them? Request the information-only urbanism certificate and start from the assumption that you need a permit.
- At the end, completion acceptance, even if you filed nothing.
This article is analysis, not legal advice. The provisions cited are from Legea 169/2026, published in Monitorul Oficial no. 661 of 10 August 2026. Check your own situation with the issuing authority.