Demolition permit: what it is and how to obtain one

Demolishing a building, in whole or in part, needs a permit, just like building a new one. The file follows the same route, on the same official forms.

Check which rules apply to you

The urbanism code applies from 25 August 2026. If you already have an urbanism certificate issued before that date, the approvals it requires follow the rules in force when it was issued.

Do you already have an issued urbanism certificate (CU)?

Your application will follow the new rules (CATUC), in force from 25 August 2026.

This result is indicative only. The exact rules for your file are determined by the issuing town hall.

The demolition permit is the document that allows a construction to be demolished, in whole or in part. It is issued under the same conditions as a building permit, with the particularities specific to demolition works. The documentation required is called PAD: the project for authorising demolition (formerly DTAD).

01

The important rule: demolition followed by a new building

If you want to put up a new building in place of the one you demolish, the town hall issues a single building permit, which approves both the demolition of the old construction and the building of the new one. In this case only the fee for the building permit of the new construction is charged: you do not pay separately for the demolition.

02

What PAD, the project for authorising demolition, contains

Written documents:

  • The list and signatures of the designers.
  • A memoriu, with a brief history of the construction (year built, characteristic data), a description of the structure, materials and architectural style, and mention of any heritage or decorative elements to be salvaged.
  • Colour photographs of all facades, of the main rooms, of the staircase and of the entrance hall.
  • A description of the demolition works.
  • A technical expert report on the demolition works, where applicable.

Drawings:

  • Site location plan.
  • Site plan, distinctly marking the constructions that remain and those being demolished, how the land is arranged after demolition, rainwater drainage, and the plantings that remain.
  • Plan of underground constructions and utility networks in the area.
  • Survey of the constructions to be demolished: the plans of all levels, the roof plan, main sections and all facades.
  • If the demolition requires complex technical operations, the works organisation project is also presented.
03

When you do NOT need a demolition permit

Demolishing household annexes or constructions exterior to single-family homes, located outside protected built-up areas, can be done through the simplified notification procedure.

04

Buildings in an advanced state of decay

The town hall can demolish constructions that are owned by the administrative-territorial unit, are in an advanced state of decay and endanger public safety. Historic monuments are excepted. The demolition is done on the basis of a demolition permit, issued under art. 302, for carrying out emergency intervention works (art. 303).

How AutoRize helps

  • Generates the F_CU_04 urbanism certificate request with demolition ticked as the purpose.
  • Fills in the F_A_01 request for the demolition permit with your project data.
  • Prepares the opis (document index), so you can see at a glance what is missing.
  • Gives you the documents in Word and PDF, ready to file at the city hall.
Generate the demolition file

Frequently asked questions

Can I demolish without a permit?

As a rule, no: demolishing a construction or part of it requires a permit, and carrying it out without a permit is sanctioned. Exception: demolishing household annexes or constructions exterior to single-family homes, located outside protected built-up areas, can be done through the simplified notification procedure.

Which form is used for a demolition permit?

The same F_A_01 form as for a building permit. The form covers the issue of both building and demolition permits, and the purpose is stated in the request.

What is PAD and how does it differ from PAC?

PAD is the technical documentation for authorising demolition works, formerly called DTAD. It is the equivalent of PAC, the project for authorising construction. Both are prepared by an authorised designer.

Do I need an urbanism certificate to demolish?

Yes. The file starts from an urbanism certificate requested with demolition as the purpose. The certificate tells you which approvals your case requires.

What does a demolition permit cost?

The fee is calculated under art. 474 of the Codul fiscal (Codul urbanismului, art. 313 para. 1) and paid to the issuing town hall. Check the exact amount with the town hall for the area the property sits in, before you file.

What happens after the demolition?

Once the works are carried out, you go through the closing procedure required by the permit, and the legal status of the property is updated in the land registry records, so they reflect what actually remains on the plot.

Prepare the demolition file

Generate the requests on the F_CU_04 and F_A_01 forms and the opis (document index), filled in with your project data.

×