Reception at the completion of works
The last stage of an authorised building: how the reception is organised, which documents are signed, and what remains to be done afterwards.
The reception at the completion of works is the set of activities for testing functionality and assessing compliance, through which the completion of the works is certified and the building is put into use.
What it involves
The site manager hands over to the owner the technical book of the building and the maintenance and component-service-life manual, drawn up under the investor's care, after which the formal reception takes place.
The documents you need
- The designers' opinion, for each specialty.
- The site manager's opinion.
- The reception reports.
- The technical book of the building.
- The use and maintenance manual by category of activity, material, structural element and equipment, with instructions for monitoring behaviour over time.
- The operator training records for the use of the equipment and installations.
- The as-built project.
The rule on hook-ups
The reception at the completion of works takes place only together with the reception of the hook-ups to technical-utility infrastructure, for individual and collective housing developments, public-utility buildings and access roads.
The technical book of the building
Drawing up the technical book in electronic format is mandatory, and it is uploaded to the National Construction Register. It is prepared under the developer's care and handed over to the beneficiary.
When the building changes ownership, the technical book is handed over to the new owner, in physical and digital format. The new owner is required to keep it up to date. For owners' associations, the technical book is kept and updated by the administrator.
The warranty period
It is set through the contract with the contractor, according to the consequence class of the building, with the following minimum durations:
- 5 years for buildings in classes CC3 and CC4.
- 3 years for buildings in class CC2.
- 1 year for buildings in class CC1.
- 2 years for planting works.
If the warranty period is not set in the contract, the minimum duration above applies automatically. The contractor is required to remedy hidden defects that arise during the warranty period.
Reception of works carried out through notificare
For works carried out under the simplified notificare procedure, the reception takes place between the contractor, the beneficiary and a representative of the town hall. A copy of the report is registered in the National Construction Register, an obligation that falls to the beneficiary. Until the register becomes operational, the copy is sent to I.S.C., physically or by e-mail (art. 298 para. 6). Registration in the land book is made based on proof that the notificare was submitted and that the register entry was verified.
Partial receptions
Partial receptions can be carried out under the conditions of the Codul urbanismului, including for works already in progress on 25 August 2026.
How AutoRize helps
- Keeps the permit, the avize and the dossier documents you need at the reception in one place.
- Shows the official deadlines of your project and sends reminders for the important dates.
- Generates the administrative documents of the dossier on the official forms, in Word and PDF.
- Reuses your project data, so you do not re-enter it at every stage.
Frequently asked questions
What is the reception at completion of works?
The stage through which the investor confirms, via a commission, that the executed works match the permit and the documentation. It ends with a reception report.
Who sits on the reception commission?
The commission is appointed by the investor and composed according to the reception regulation, with the parties involved in the work taking part. The concrete composition depends on the type and category of the building.
What happens if there are objections?
The commission can admit the reception with objections, recording what must be remedied and by when. It can also reject the reception, in which case the process resumes at the set date.
Why do I need the reception report?
It is the document on which the permit fee is regularised, the building is declared for taxation and the registration in the land book can be made.
Is the final reception mandatory?
Yes, it is the second stage provided by the regulation and takes place when the warranty period expires, checking how the works behaved and whether earlier objections were remedied.