RECEPTION OF WORKS

Reception at the completion of works

The last stage of an authorised building: how the reception is organised, which documents are signed, and what remains to be done afterwards.

The reception at the completion of works is the set of activities for testing functionality and assessing compliance, through which the completion of the works is certified and the building is put into use.

01

What it involves

The site supervisor (diriginte de șantier) hands over to the owner the technical book of the building and the maintenance and component-service-life manual, both of which the investor is responsible for having drawn up, after which the formal reception takes place.

02

The documents you need

  • The designers' opinion, for each speciality.
  • The site supervisor's opinion.
  • The reception reports.
  • The technical book of the building.
  • The use and maintenance manual by category of activity, material, structural element and equipment, with instructions for monitoring behaviour over time.
  • The operator training records for the use of the equipment and installations.
  • The as-built project.
03

The rule on utility connections

The reception at the completion of works takes place only together with the reception of the connections to the utility infrastructure, for individual and collective housing developments, public-utility buildings and access roads.

04

The technical book of the building

Drawing up the technical book in electronic format is mandatory, and it is uploaded to the National Construction Register. The developer is responsible for having it prepared, and it is handed over to the beneficiary.

When the building changes ownership, the technical book is handed over to the new owner, in physical and digital format. The new owner is required to keep it up to date. For owners' associations, the technical book is kept and updated by the administrator.

05

The warranty period and final reception

The warranty period is set through the contract with the contractor, according to the consequence class of the building, with the following minimum durations:

  • 5 years for buildings in classes CC3 and CC4.
  • 3 years for buildings in class CC2.
  • 1 year for buildings in class CC1.
  • 2 years for planting works.

If the warranty period is not set in the contract, the minimum duration above applies automatically. The contractor is required to remedy hidden defects that arise during the warranty period.

The warranty runs from the signing of the reception report at the completion of works (art. 531 para. 9). When it expires, final reception follows, the second mandatory stage of reception (art. 527 para. 2 lit. b): the beneficiary organises it within at most 10 days (art. 532 para. 4). Failing to hold final reception is a contravention, fined 50,000 to 100,000 lei, with no option of a warning instead (art. 570 para. 1 lit. k, para. 2 lit. a and para. 3). The reception regulation in HG 273/1994 stays in force until it is amended (art. 577 para. 6).

06

Reception of works carried out through notificare

For works carried out under the simplified notificare procedure, the reception takes place between the contractor, the beneficiary and a representative of the town hall. A copy of the report is registered in the National Construction Register, an obligation that falls to the beneficiary. Until the register becomes operational, the copy is sent to the Inspectoratul de Stat în Construcții (ISC), physically or by email (art. 298 para. 6). Registration in the land book is made based on proof that the notificare was submitted and that the register entry was verified.

07

Partial receptions

Partial receptions can be carried out under the conditions of the Codul urbanismului, including for works already in progress on 25 August 2026.

How AutoRize helps

  • Keeps the permit, the avize and the dossier documents you need at the reception in one place.
  • Shows the official deadlines of your project and sends reminders for the important dates.
  • Generates the administrative documents of the dossier on the official forms, in Word and PDF.
  • Reuses your project data automatically, so you do not re-enter it at every stage.
Start free

Frequently asked questions

What is the reception at completion of works?

The stage through which the investor confirms, via a commission, that the executed works match the permit and the documentation. It ends with a reception report.

Who sits on the reception commission?

The commission is appointed by the investor and composed according to the reception regulation, with the parties involved in the work taking part. The exact composition depends on the type and category of the building. The Codul urbanismului expressly requires a representative of the authority that issued the building permit to take part (art. 280 para. 3).

What happens if there are objections?

The commission can admit the reception with objections, recording what must be remedied and by when. It can also reject the reception, in which case the process resumes at the set date.

Why do I need the reception report?

It is the document that certifies the works are finished and on which the land-book registration can be made. The tax declaration cannot wait for it indefinitely: the acquisition date is the date of the reception report, but no later than the 15th day after the works are actually finished, and the declaration is due within 30 days of that date (Codul fiscal, art. 461 para. 2 and para. 3 lit. a). The permit-fee regularisation comes before the reception, within 15 days of completing the works (Codul fiscal, art. 474 para. 7 lit. c; Codul urbanismului, art. 280 para. 9).

Is the final reception mandatory?

Yes. The beneficiary organises the final reception within at most 10 days of the warranty period expiring (Codul urbanismului, art. 532 para. 4). The final reception commission can close the warranty period or extend it until defects not caused by improper use are fixed (art. 532 para. 3). The detailed procedure remains the one in the reception regulation approved by HG 273/1994, which applies until it is amended (art. 577 para. 6).