The difference between a geotechnical study and a geotechnical expert report is not one of size. They are different documents, required in different situations, and the code sets three numeric thresholds that decide which.
The context is authorising amenajare works, and the full list of complementary documentation is in article 289 paragraph (2). What goes into the building-permit dossier itself is on the PAC page.
The thresholds
A geotechnical expert report is required in three situations, under letter b):
- when the necessary excavation goes deeper than 6 m, measured from natural ground level;
- when works are carried out on difficult foundation ground, on a slope with landslide potential;
- when retaining walls higher than 3 m are built.
Letter a), the geotechnical study, does not depend on these thresholds; above them the expert report is added. The figures are written in the law, not inferred. The 3 m threshold concerns the permit file; the article 299 exemption for retaining walls inside the yard has no threshold, as shown in retaining wall and access steps.
The loop most people miss
The text does not stop at the expert report. If it recommends slope-support elements or improvement of the foundation ground, then for authorisation a geotechnical and structural study is submitted, describing the designed solution in principle, without detailing it.
So in the hard case you end up filing both, and the second document comes after the first and depends on its conclusions. That is sequencing, not bureaucracy: you cannot commission both on the same day, and you cannot estimate the timeline before knowing what the report recommends.
Without detailing is not a loophole
The wording limits what is required for authorisation, not what gets built. The detailed solution belongs to the next phase, the technical execution project. Commissioning a full support design at permit stage pays for a phase that cannot yet be finished.
And for building?
The thresholds above are written for site works. For building, the code puts the two documents in different places in the file:
- the geotechnical study appears from the start, in stage 1, among the preliminary site studies (article 491 paragraph (3) letter a)), and then as complementary documentation for the building permit (article 265 paragraph (2) letter a)). For works on existing buildings it includes stripping, boreholes and trial pits at the foundations, plus the verification report for the Af requirement;
- the geotechnical expertise goes into the specific engineering project only where needed (annex no. 2, point 1.6 letter a)), next to the calculation notes and the expertise on the effect on neighbouring buildings.
For building, the code sets no numeric thresholds as it does for site works, and does not say who decides when the expertise is needed. Our reading: the order stays the same, the study first, then the expertise if the study’s conclusions call for it.
What we check first
Excavation depth against natural ground level rather than finished level, and the height of the retaining walls. Two numbers move a dossier from one category to the other, and both are known at concept stage. The boundary between authorisation and execution is in the permit project is not the build project, the drawing that accompanies them is in the site plan, and the order they arrive in is in the order of the steps. For interventions on existing buildings, where diagnosis comes before the solution, see technical expert reports.
This article is analysis, not legal advice. The provisions cited are from Legea 169/2026, published in Monitorul Oficial no. 661 of 10 August 2026. Check your own situation with the issuing authority.