A pond dug in your garden (iaz) usually needs a building permit: the Urbanism Code puts it in no list of works, but counts excavations among landscaping works (lucrări de amenajare). In a village, inside the built-up area and outside the metropolitan areas, the notification route for pools and similar structures probably covers it, if together with the other new structures in the garden it stays within 50 sq m. Separately, the Water Law requires an aviz from Apele Române for a pond dammed on a stream or fed by diverting it and, probably, for one that takes more than the household threshold from a spring or a borehole.
In short
| Question | Answer | Source |
|---|---|---|
| Does the Urbanism Code name the pond? | No, in no list of works | Legea 169/2026, art. 294, 299 |
| So what is the excavation? | A landscaping work, which needs a permit unless the law exempts it | Legea 169/2026, art. 259 para. (2) letter c), (4) and (6) |
| Is there a lighter route in a village? | Probably the notification, as “the like” next to pools, at most 50 sq m in total | Legea 169/2026, art. 294 para. (2) letter a) point (i) |
| When do you need the Apele Române aviz? | For impoundments and for works that use water, including fish-farming or leisure facilities; our reading: it turns on the water source | Law 107/1996, art. 48 para. (1) letters a)-b), art. 50 para. (1) |
| What escapes the aviz? | Household use with no installations or at most 0.2 litres per second | Law 107/1996, art. 9 para. (2), art. 50 para. (3) |
| What is the fine without the aviz? | 10,000-15,000 lei for a private individual | Law 107/1996, art. 87 point 1), art. 88 para. (1) letter b) |
What the Urbanism Code does with a pond
The Code (Legea 169/2026) mentions ponds once, in a planning definition, that of green-blue infrastructure in annex 1. You will not find the pond among the works that go by notification (article 294), nor among those that need no formality at all (article 299).
That leaves the general rule. Article 259 paragraph (2) splits construction works into three categories, and the third is landscaping works. Paragraph (4) lists among landscaping works both works that affect the way the land is used and excavations. A pit of a few cubic metres, lined with foil or concrete and kept full of water, is an excavation and changes how that part of the plot is used. Our reading is that a dug pond falls here. Paragraph (6) then says the permit is mandatory, except for construction works for which the law allows notification or no formality at all.
Not every container of water is a work. Annex 1 defines a construction as a work made of any structure fixed in or on the ground. A plastic tub set on a terrace, with no excavation and no foundation, is fixed neither in nor on the ground, and our reading is that it needs no paper at all.
The list of works with no formality also includes landscaping of front gardens, outside protected built-up areas (article 299 paragraph (2) letter b) point 2), but the same work also appears among the landscaping works that go by notification (article 294 paragraph (4) letter g)). The Code does not say what a front garden covers and does not define it in annex 1. For a pond behind the house the text does not help at all; for one in front of it, ask the town hall before relying on the exemption.
Notification in a village: where the pond fits
Article 294 paragraph (2) letter a) point (i) accepts by notification new structures outside the house, listed as garages, covered terraces, pergolas, summer kitchens, kiosks, pools, sanitary blocks and the like, up to 50 sq m in total. The pond is not on the list, but the list is open. A water basin dug next to the house is, on our reading, close enough to a pool to count as “the like”; the town hall may read it otherwise, and the text does not settle it. This route assumes that the lined pond is also a construction, like the pool, because the separate list of landscaping works that go by notification (article 294 paragraph (4)) does not include the pond.
If the pond fits there, it takes on every condition the pool has: a rural area, inside the built-up area (intravilan), a locality outside the metropolitan areas (except for rural localities in metropolitan areas), outside protected areas and the protection zones of historic monuments, with approved urbanism plans, and with its area added to the other new structures in the garden. Each condition is explained, with examples, in the article on a garden pool. In a town, above the threshold, or when any other condition fails, the building permit applies.
Notification does not spare you a design. The form goes in with a simplified technical design, and the steps and deadlines are on the page on simplified notification.
When Apele Române comes in
The second paper does not come from the town hall. Article 48 paragraph (1) of the Water Law (no. 107/1996) lists the works built on waters or connected with waters. Letter b) covers works that use waters, among them fish-farming facilities and spa, tourist or leisure facilities. Letter a) covers impoundments, that is water held back behind a dam or a dyke. Article 50 paragraph (1) says all of these go ahead only on the basis of the water management aviz (aviz de gospodărire a apelor), and are put into operation only on the basis of the water management authorisation. In the Water Law’s own sense, an iaz proper is such a work: annex 1 (point 86) defines it as a lake created by diverting a watercourse or by damming a watercourse, with a small dam. A garden basin filled some other way shares the name only in everyday speech; our reading is that this definition does not catch it.
The law sets no size below which a pond escapes the aviz. The aviz procedure, approved by Order 828/2019, sets none either: its table of works (annex 1.a) lists fish-farming and leisure facilities with no size at all. The aviz is requested before works begin (article 2 paragraph (2) of the procedure) and lapses if works have not started within 2 years (article 27). It is issued by the river basin administrations, and the county water management systems issue it within the powers the basin administration delegates to them (annex 1.c).
Our reading is that the key is where the water comes from. The list in letter b) opens with works that use waters, and we read it as concerning works that draw water from a resource: a river, a spring, groundwater. The text does not say so explicitly.
Mains water, your well or a stream
From the public network. A pond filled from the tap draws nothing from a resource; it takes water from an operator that holds its own authorisation. Such a pond is not, on our reading, a work that uses water, and needs no aviz.
From your own well or borehole. Article 9 paragraph (2) leaves free the use of surface or ground water for drinking, watering animals, watering, washing, bathing and other household needs, if no installations are used or if the flow does not exceed 0.2 litres per second, exclusively to meet the needs of one’s own household. Article 50 paragraph (3) takes exactly these uses out of the aviz requirement. 0.2 litres per second is 720 litres an hour, so a 10 cubic metre pond fills at that rate in about 14 hours. The text does not say whether an ornamental pond is a household need. Watering the garden is one, and topping up what evaporates in summer is close to it; our reading is that a small household pond fits here, but if you want certainty, ask the county water management system in writing.
From a spring or a stream. A pond dammed across a watercourse, or fed by diverting one, is an impoundment or a work that uses water, so it needs the aviz. For any dam, paragraph (1^1) of article 50 adds a safe operation agreement, and the Urbanism Code bans construction in minor river beds, except for water management works (article 171 paragraph (2)). If you only take a little water from a spring, with no installations or at most 0.2 litres per second, article 9 paragraph (2) covers it just as it covers well water. Owning the bed does not take the stream out of the water rules: the beds of streams shorter than 5 km, with a catchment of at most 10 sq km and water that does not flow all year, belong to whoever holds the land (article 3 paragraph (2)), but even then the owner must use the water in line with the general conditions for water use in that basin.
With fish. The Water Law does not define a fish-farming facility. A pond with a few ornamental fish is not, on our reading, one of them. A pond where you raise fish to eat comes close to it: if it takes water from a natural source it goes to the aviz, and if it is filled from the mains, ask the water management system before you stock it.
Next to a stream: the protection strip
A pond dug on the bank of a watercourse has one more problem. Article 40 sets protection strips along river beds, and annex 2 of the Water Law gives their width: 5 m for a watercourse narrower than 10 m, 15 m between 10 and 50 m and 20 m above 51 m (2, 3 and 5 m for regulated watercourses). The restricted use of those strips is applied by Apele Române, following a ministry methodology (paragraph (3)), and article 49 paragraph (1) bans new homes or their outbuildings in them. The text does not say whether a pond is an outbuilding of the home; our reading is that if you treat it like a pool on the notification route, the ban covers it too. If your plot has a stream at the end, check first where the protection strip ends and only then choose where the pond goes.
What you risk if you dig without papers
There are two different fines, from two different authorities. On the urbanism side, article 357 paragraph (4) of the Code provides 5,000 to 50,000 lei for works done without the required notification (letter a)) and 50,000 to 1,000,000 lei for works done without the required building permit (letter b)).
On the water side, article 87 point 1) of the Water Law makes it an offence to carry out or put into operation a work connected with waters without the aviz or the authorisation, and article 88 paragraph (1) letter b) fines a private individual 10,000 to 15,000 lei for it. It is found by, among others, Apele Române inspectors and Environmental Guard commissioners (article 90). If the pond is already there, the ways back into legality on the urbanism side are on the page on the regularisation permit.
The spot, the area and the water source
- Find out from the urbanism certificate or the town hall whether the plot is intravilan, in a commune outside the metropolitan areas, outside protected areas and monument protection zones, and whether it has approved urbanism plans.
- Add the pond’s area to that of the other new structures in the garden and compare the total with the 50 sq m threshold.
- Decide where the water comes from: the mains, a household take (no installations or at most 0.2 litres per second), a larger take, or a diversion or dam on a watercourse. For the last three, ask for the aviz before you dig.
- If a watercourse runs past the plot, measure the protection strip from annex 2 and keep the pond outside it.
This article is analysis, not legal advice. The provisions cited are from Legea 169/2026, published in Monitorul Oficial no. 661 of 10 August 2026 (with the rectification in Monitorul Oficial no. 862 of 14 October 2026), from the Water Law no. 107/1996, in its form consolidated on 23 July 2026, and from the procedure approved by Order 828/2019. Romanian legal terms are kept in the original where the English would be misleading. Check your own situation with the issuing authority.