For public investments in buildings that fall under the Urbanism Code, the feasibility study (studiul de fezabilitate) compares sites and scenarios and ends with the approval of the technical and economic indicators (articles 492-496). The Code no longer requires it to include the plans, sections and elevations that HG 907/2016 required, and the Ministry of Development stated in October 2026 that it need not contain them. The cost is estimated from a reference index plus the budget margin, once the ministry’s application is operational. Design starts at the next stage.
HG 907/2016 and the Code, side by side
| HG 907/2016 | The Code (Legea 169/2026) | |
|---|---|---|
| Place in the process | After the concept note and the design brief (art. 3, 4 and 7) | Stage 1, before design (art. 479(1)(b)) |
| How many scenarios | At least two (art. 7(1)) | The number set in the design brief (art. 495(1)(b)) |
| What the recommended scenario describes | The technical solution (art. 7(2)(a)) | Functional proposals in principle (art. 495(3)(b)) |
| Drawings | Site plan, general plans, dimensioned elevations and sections, massing (annex no. 4, part B) | Graphic representations (art. 495(1)(e)); according to the ministry, analysis only |
| The cost | Market prices or cost standards applied to estimated quantities (annex no. 4, item 3.3) | Reference index plus budget margin (art. 494(3)) |
| Approval | Under Legea 500/2002 and Legea 273/2006 (art. 7(7)) | The same (art. 496(6)) |
What a feasibility study is in the Code
The feasibility study is the stage 1 document that develops the design brief and makes the case for the investment. The Code splits the life of an investment into stages: stage 1 means defining the design brief and determining feasibility, and belongs to the initiation phase, while design proper starts with stage 2, in the planning phase (article 478(3) and article 479).
Article 492(1) defines it as a development of the design brief: it identifies the best site and the best scenario and justifies the economic and financial case for the investment, taking into account the costs of similar projects. It is compulsory for works financed wholly or partly from public funds (paragraph (2)). It is not compulsory for emergency interventions, routine repairs and maintenance, or works that go by notification or need no formality at all (paragraph (3)). If the study shows the investment is not viable, the brief is redefined or the project is dropped (paragraph (4)).
Article 492(2) makes it compulsory for public funds and says nothing about private ones. Our reading: for an investment financed wholly from private funds, the study is not compulsory. The substantiation note and the strategic brief then go into a business plan, and that plan is optional (article 487).
What it contains: sections, analyses, indicators
The framework content has six sections (article 495(1)): the existing situation and the need for the investment, the proposed scenarios, the choice and detailed presentation of the best scenario, strategies and recommendations, graphic representations, and conclusions. For each scenario it sets out the particular features of the site, the technical and functional characteristics required by the brief, the estimated costs and the results of the specialist studies (paragraph (2)).
The minimum analyses are those in article 494: analysis of the elements of the brief, the specialist studies and the cost estimate. The specialist studies cover the financial and economic analysis, the sustainability analysis, the demand analysis and the risk analysis, plus other analyses as needed.
The best scenario comes with four technical and economic indicators (article 496(1)): the total estimated value; the minimum performance and quality indicators; the financial, socio-economic, impact, result or operating indicators; the estimated duration of the works. The presentation of the best scenario also attaches the urbanism certificate as a supporting document (article 495(3)(d)). The design brief requires one certificate for each site under consideration (article 490(3)). What the application involves is on the page about the urbanism certificate.
Why the Code no longer asks for plans and elevations
The list of sections asks for graphic representations without saying what kind. The ministry was asked directly whether the document is only an analysis supporting the investment, with no design drawings, and answered yes. In its answer, the representations are analytical: location, site analysis, diagrams of functional relationships, area schedules. The dimensions required by the design brief (article 491(2)(b)) mean, again according to the ministry, the required floor areas, within the limits of the planning rules.
The ministry’s conclusion: the feasibility study establishes whether, where and within what limits of cost, performance and time the investment is made. It does not establish what the building looks like.
Our reading: the text supports the answer, but not fully. Plans of every level, sections, elevations and massing models are listed in the Code as the drawings of the project concept, the documentation of stage 2 (article 500(3)). Article 495 has no such list. It still remains a matter of judgement, because each scenario must also be described by its technical, constructional, functional characteristics, and how much drawing that takes is not stated anywhere.
The difference from practice so far is large. HG 907/2016 requires, in part B of annex no. 4, a location plan, a site plan, general plans, dimensioned characteristic architectural elevations and sections, outline schemes for structure and services, and massing. The recommended scenario there includes the technical solution. In the Code, the same place is taken by functional proposals in principle, to be detailed in the following stages (article 495(4)).
How the cost is estimated, now and after 2027
Until the ministry’s application that generates the reference indices is operational, costs are substantiated under the law in force when the Code was approved (article 577(4)). Article 418(5) schedules the application for 1 September 2027. The ministry says its absence does not hold up feasibility studies and that only the source of the cost data changes.
After that, article 494(3) requires the cost of the works to be estimated by reference to the index generated under article 418, plus the budget margin. The cost of design is estimated as a percentage of the cost of the works (paragraph (4)). The ministry stresses that the estimate is not made from quantity take-offs of a design solution.
For public works, the margins are in annex no. 8 to the Code. At the stage of the design brief and the feasibility study, the margin for buildings is +25%. We explained how to read the table, and what the margin leaves out, in the budget margin by stage, using the parallel table for private works, which reads the same way.
Which projects stay on HG 907/2016
The Code’s stages do not apply to investments made under HG 907/2016 that are in one of the four situations in article 577(1): works under way when the Code took effect; procurement already launched or documentation already accepted or filed for approval; funding approved; accepted documentation that has to be updated. For them the law in force at the date of that situation applies (paragraph (2)).
Transport infrastructure projects also have rules of their own in the Code. Article 338(2) requires a pre-feasibility or feasibility study for them, followed directly by the design for the building permit and the technical design for execution, and article 333(5) refers to the outline approval given at the feasibility study stage under Government Decision no. 907/2016. This post covers buildings only.
For all other public investments, the ministry says the Code’s rules apply, with their stages. Again according to the ministry, HG 907/2016 still applies only to the extent it does not contradict the Code, and its requirements for solution drawings at the study stage no longer apply. The decision has not been amended since the Code: on the official portal, the latest recorded amendment is HG 1116/2023. We went through the four situations in the article about the building permit in EU-funded projects.
That leaves, side by side, a government decision, unamended, that asks for plans and elevations, and a law that, for buildings, no longer does. Only the ministry’s clarification links them, and it has no number and is not an order. If the funder or the call guide still asks for a study on the model in the decision, ask the funder in writing what content it accepts.
Where the design competition fits
According to the ministry, stage 1 ends with the approval of the technical and economic indicators. Only then comes the project concept, which, for investments financed from public funds, may be the result of a design competition run under public procurement rules (article 498(6)).
The ministry recommends that the competition be for the concept, run after the indicators are approved, on the basis of the initial brief and the study, both prepared by the organiser. The contract awarded to the winner may cover developing the concept, the design for the building permit, the technical design for execution, the working details and technical assistance. According to the ministry, the study should not be part of that contract, because it comes before the competition and underpins it.
For a design practice
Three things change from what practices are used to under HG 907/2016.
The first is the drawings. Plans, sections and elevations are delivered at the concept, in stage 2, on the list in article 500. According to the ministry, a fee proposal that promises them at the study stage promises more than is needed.
The second is the cost. The bill of quantities gives way to an estimate from an index plus a margin, and until the ministry’s application is operational (article 418 schedules it for 1 September 2027), the data source stays the one from before the Code.
The third is the order. According to the ministry, the indicators are approved before any design phase and include no parameters derived from an architectural solution. The design that goes to the permit is prepared in stage 3, on the content in annex no. 2, described on the page about the design for the building permit.
This article is analysis, not legal advice. The provisions cited are from Legea 169/2026, published in Monitorul Oficial no. 661 of 10 August 2026 (with the rectification in Monitorul Oficial no. 862 of 14 October 2026), from HG 907/2016, in its form on the official portal on 13 November 2026, and from the second set of clarifications on the Code, published by the Ministry of Development on its website and read on the same date. Romanian legal terms are kept in the original where the English would be misleading. Check your own situation with the issuing authority.