The Urbanism Code, the reception regulation and the Fiscal Code give three different acts the name partial reception report. Which applies and what it holds.

Citește în română

Three different acts go by the name partial reception report (proces-verbal de recepție parțială). In the Urbanism Code (Legea 169/2026), partial reception means handing over a finished, independent part of the building, in a building at least one tronson. The reception regulation that is still in force uses the same name for the act recording the physical stage of unfinished works, which the Code calls reception by physical stage of execution. The Fiscal Code gives the same name to the report on which the tax on an unfinished house is set when the permit expires. The template forms that circulate online are, as a rule, copies of the regulation’s template.

The three acts, briefly

The actWhat it recordsWhen it is doneWhere it is written
Partial reception under the CodeA finished part, physically and functionally distinct and independent; in a building, at least one tronsonWhen that part is finished and, separately, at the end of its warrantyLaw 169/2026, art. 527(3); Annex 1
The physical-stage report (the regulation’s)The physical stage of unfinished works, for land-register registration or when the beneficiary takes over an unfinished partAt any time before completionReception regulation, art. 6(d), art. 7, annex no. 1; Law 169/2026, art. 280(6), art. 527(6)
The Fiscal Code’s reportThe floor area that has walls and a roofOn the date the permit expires, for an unfinished buildingFiscal Code, art. 461(3)(c)

The first is a real reception, with the same stages as the reception of the whole building. The other two record how far unfinished works have got.

Partial reception in the Urbanism Code

The rule is that reception has two stages: at completion of the works and final, when the warranty runs out (art. 527(2)). Paragraph (3) allows reception to be carried out separately for parts, objects, sectors or tronsoane covered by the permit. They must be physically and functionally distinct and independent, safe to use and compliant with the fundamental requirements. For civil engineering works the Code sets no limit on the size of the part; in a building the part received must be at least one tronson.

The beneficiary decides, at the contractor’s request and with the designer’s opinion. Partial reception follows the same steps as an ordinary reception, but only for the part received, and it too has two stages: at completion and final. It can be done for a part that merely meets the conditions to enter service, not only for one about to be used (art. 527(3)). Article 574 also allows partial receptions for works under way on 25 August 2026, the date the Code came into force, on the Code’s terms. Our reading is that the tronson limit for buildings therefore applies too.

The Code does not define tronson: the word appears only in article 527 and in the Annex 1 definitions. Our reading is that one floor or one flat in a block cannot be received on its own, because it is not a tronson. On the same reading, a separate building under the same permit, such as a garage next to the house, is a free-standing structure, and so at least one tronson. The page on reception at completion of works sets out the reception procedure that the part received also follows.

The physical-stage report, which the regulation calls partial

The beneficiary may decide, giving reasons, to take over from the contractor part of the building at a given physical stage of execution (art. 527(6)). The report must record, as applicable, the state of the part taken over, the defects found with the remedy deadlines, and the measures to preserve the works (para. (7)). The definitions in Annex 1 to the Code say plainly that this act concerns a part that does not meet the conditions for partial reception. The reception regulation gives this act the name partial reception.

The regulation, annexed to HG 273/1994, stays in force until it is amended (art. 577(6)). We read it in the text of 18 May 2017, published in Monitorul Oficial no. 406 of 30 May 2017, in the form applicable on 11 October 2019, the latest we could read. The regulation makes its partial reception act the one attesting the physical stage of execution. Its stated purpose is registering ownership in the land register, and the act is identified with the report recording the stage of the building (proces-verbal de constatare privind stadiul realizării construcției) under Legea 7/1996 (art. 6(d)). The mandatory content is the same as in the Code (art. 7(2)), and at the reception at completion the beneficiary hands the report to the reception committee (art. 8).

The Code itself mentions these acts together. Article 280(6) says that, until the works are finished, partial reception reports or physical-stage reports may be drawn up, together with (respectiv) the report recording the stage of the building. Article 527(9) requires the report recording the stage of the building to hold the same information as the physical-stage report under paragraph (7).

What the regulation’s template contains

Annex no. 1 to the regulation is the template you find when you search for proces verbal de recepție parțială. It has seven points:

  1. The property: administrative address, cadastral or topographic number, land register number.
  2. The building permit: number, issuer, date and validity.
  3. Other people present, besides the contractor and the investor, with name, capacity and signature.
  4. The secretariat, kept by the site supervisor (diriginte de șantier), with the field and number of their licence.
  5. The physical stage of execution.
  6. Other remarks.
  7. The number of pages, annexes and copies, with the date it was signed.

The contractor and the investor, that is the beneficiary, sign it. Point 5 is the one that matters: it holds the state of the works, the defects with their remedy deadlines and the preservation measures required by art. 7(2) of the regulation, worded as in art. 527(7) of the Code. To register an unfinished house in the land register, Legea 7/1996 also requires the certificate of the stage of the building and the cadastral documentation, described, alongside the certificate for a finished house, in the certificate of completion.

The report under the Fiscal Code

The third meaning concerns tax. If the permit expired by 31 December of the previous year, without an extension and without the issuer being told that the works cannot be finished in time, tax on the unfinished house is set on the floor area that has walls and a roof. The basis is a report of that name drawn up compulsorily on the date the permit expires. If you build without a contractor, you notify the town hall so that it takes part (Fiscal Code, art. 461(3)(c)).

The whole case is in a house with no reception report.

Which act you need, by situation

If you want to move into a finished, independent part, such as one house of a semi-detached pair built as two tronsoane, you need the Code’s partial reception, with the report signed when that part is finished. Putting a building into use requires the reception at completion to be accepted (art. 527(4)). The part received also has its own, separate final reception (art. 527(3)).

The final reception is covered in the final reception after the warranty.

If you want to register an unfinished house, you need the physical-stage report, that is the template in annex no. 1. When you take over an unfinished part, for instance to preserve the site over the winter, you may draw it up by your own reasoned decision (art. 527(6)). If the permit expired with the house unfinished, tax is set on the basis of the Fiscal Code’s report.

A house built without a contractor has nobody to request a partial reception, and article 527(3) starts from the contractor’s request. The Code does not deal with that case separately. For the ordinary reception of such a house, see reception of a self-built house.


This article is analysis, not legal advice. The provisions cited are from Legea 169/2026, published in Monitorul Oficial no. 661 of 10 August 2026, from the regulation on the reception of buildings annexed to HG 273/1994, in the text given by HG 343/2017, and from the Fiscal Code. We could not check any amendments to the regulation after 11 October 2019. Romanian legal terms are kept in the original where the English would be misleading. Check your own situation with the issuing authority.

AutoRize Team

The AutoRize team

We write about construction permitting in Romania: what has changed, what it means for your file and what to do now.

Your certificat de urbanism file, in 30 seconds

AutoRize generates the application, the memoriu de prezentare and the opis for the certificat de urbanism, matched to local planning rules.

Get started