Anyone searching “HG 273/1994 final reception” is typing the title of an old regulation and wants to know what applies today. The short answer: the final reception (recepția finală) exists in the Urban Planning Code (Legea 169/2026), and the regulation in Government Decision 273/1994 stays in force until it is amended. The Code itself fixes a few things: how long the minimum warranty lasts, who organises the reception and within what time. The page on the completion acceptance already gives the short answer to “is the final reception mandatory?”. Here I go further.
What stays of HG 273/1994
Article 577 para. (6) says that the annex “Regulation on the reception of constructions” to HG 273/1994, as amended and supplemented, stays in force until that regulation is amended. The same paragraph also keeps HG 845/2018, for reception in national road and rail infrastructure. The general mechanism is in what the Urban Planning Code repealed.
The Code does not list the amendments. The Code says nothing about HG 343/2017, and I have not checked its text here, so I do not say what it changes or how it relates to HG 273/1994.
Article 528 para. (5) refers to the reception regulations, but only for the procedure of the reception at completion. Article 532, on the final reception, makes no such referral. Who sits on the commission and what form the minutes take is not written in the Code (I searched; it does not appear). The regulation kept in force by article 577 para. (6) is where one would look, but its text is not among what I verified, so I cannot tell you what it says.
The two stages, and where the final reception sits
Reception of constructions of any category is carried out by the beneficiary or developer and has two stages: at completion of the works, and final, at the end of the warranty period (art. 527 para. (2)). For buildings with at least one distinct, independent section, partial receptions are possible, including a partial final reception (para. (3)). The partial route is an exception, so the rule stays two stages.
The final reception is the last step of stage 6, “handing over the construction”. That stage begins right after the completion acceptance and closes with the final reception (art. 531 para. (1)). The works count as finished after the completion acceptance (art. 280 para. (1)), so the final reception does not condition moving in. I also found no exception in arts. 527, 528 or 531 for a house built in-house, nor a rule on what the warranty looks like when there is no contractor; that case is in acceptance of a house built in-house.
How long the warranty lasts
The warranty period is written into the contract with the contractor and has minimum lengths by consequence class (art. 531 para. (6)-(7)):
| Constructions | Minimum warranty |
|---|---|
| CC3 and CC4 | 5 years |
| CC2 | 3 years |
| CC1 | 1 year |
| Planting works | 2 years |
Five more rules from the same article:
- If the contract is silent, the minimum for the building’s class applies (para. (7)).
- The warranty starts on the date the completion-acceptance minutes are signed (para. (9)).
- It is extended by an addendum with the time needed to fix defects that appeared during the warranty (para. (8)).
- The contractor must fix hidden defects that appear during the warranty (para. (3)).
- For structural defects the warranty runs for the whole life of the building (para. (10)).
How the class of a house is set is in consequence class, and what the contract secures for you is in the construction contract for a house.
What the final reception commission decides
The evaluation at the end of the warranty can run in one or more sessions and ends with convening the final reception commission (art. 532 para. (1)-(2)). The commission has two options (para. (3)): close the warranty period and sign the minutes, or extend the warranty until defects are fixed, where those defects do not come from improper use. Defects you cause through use therefore do not extend the contractor’s warranty.
Who sits on the commission, the Code does not say. I searched the whole text of the law: the final reception commission is named only in art. 532 para. (2), and para. (3) repeats it, with no composition. The representative of the permit issuer is required expressly only at the completion acceptance (art. 280 para. (3)); for the final one I find no rule. The composition is left to the regulation.
The 10 days, and what if you miss them
The beneficiary must organise the final reception within 10 days of the date the warranty period expires (art. 532 para. (4)). The article does not say what follows if the deadline passes, but the Code has a sanction for not carrying out the final reception. Failure of the developer or beneficiary to hold the final reception at the end of the warranty is a contravention (art. 570 para. (1) lit. k)), with a fine of 50,000 to 100,000 lei and no option of a warning (para. (2) lit. a) and para. (3)), established by I.S.C. (art. 571 para. (1)). The text speaks about the final reception in general, not about the 10 days, so I cannot say whether a delay of a few days is sanctioned the same way. Read the fine as a reason not to put it off, not as a prediction.
What is handed over at the final reception
The technical file of the building is handed over in two parts. At the final reception come the reception documentation, the documentation on monitoring behaviour in use and on interventions, the user manual and the operating specifications (art. 530 para. (2) lit. b)); failure by the developer to hand them over is also a contravention (art. 570 para. (1) lit. r)). The second part is described in the technical file goes electronic. After the final reception the beneficiary’s duty to monitor the building over time remains, covered in the obligation that starts after you move in.
The order in which to check
- The house’s consequence class, from the design, and the warranty in the contract (minimum 1, 3 or 5 years).
- The date the completion-acceptance minutes were signed: the warranty runs from it.
- Defects that appear before expiry, noted in writing, so an extension can be requested.
- Organising the final reception within 10 days of the warranty expiring (art. 532 para. (4)).
- The technical file completed with its second part.
This article is analysis, not legal advice. The provisions cited are from Legea 169/2026, published in Monitorul Oficial no. 661 of 10 August 2026. The content of HG 273/1994 and HG 343/2017 was not checked. Check your own situation with the issuing authority.