A house with no reception report: what you risk

Without a reception report, a house is not legally finished: using it draws a fine, building tax is due anyway and land registration waits. How to put it right.

Citește în română

The house is finished, furnished, and perhaps you have lived in it for a year. The reception report at completion of works (procesul-verbal de recepție la terminarea lucrărilor) was never signed, either because one approval was missing or because nobody called the reception committee. Its absence has four separate consequences: the works are not finished in the legal sense, using the house is an offence, building tax is due anyway, and the house cannot be entered in the land register as a finished building.

What happensWhat the law saysWhere it is written
Status of the worksWithout reception, the works are not considered finishedUrbanism Code, art. 280(8)
Using the houseAn offence, fined 50,000 to 100,000 leiUrbanism Code, art. 570(1)(l)-(m), (2)(a)
Building taxDue anyway: acquisition dates from 15 days after completion at the latest, and since 2026 the town hall can also find the house finished or in use itselfFiscal Code, art. 461(3)(a) and (1^1)(a)
Land registrationThe certificate it rests on presupposes a reception reportLaw 7/1996, art. 37(1)
The permitLapses if the works are not finished within the execution period and no extension was requested; whether that reaches a house that is built but not received is unclear (see below)Urbanism Code, art. 310(2)

What your house is, legally, until reception

The Urbanism Code (Legea 169/2026) ties completion to reception, not to the last coat of paint. Works count as finished when everything in the permit and the technical execution design has been built and the reception at completion has taken place (art. 280(1)). Paragraph (8) says the same from the other side: without reception, the works are not considered finished.

The definitions in Annex 1 to the Code go further. An existing building (construcție existentă) is one whose reception at completion was admitted, or one entered in the land register after the prescription periods ran out. A house that is lived in but never received fits neither. How completion links to the notice you send the town hall is covered in the start and completion notices.

Moving in before reception is fined

This is the part missing from almost every explanation, because the sanction does not sit in the chapter on permits. Article 570(1) makes two acts by the owner an offence: putting the building into use (letter (l)) or allowing it to be used (letter (m)) before the reception at completion has been admitted or before the utility connections are in service. Either condition missing is enough. The fine is 50,000 to 100,000 lei under paragraph (2)(a), and paragraph (3) rules out a mere warning.

The offence is established by the inspectors of the State Construction Inspectorate, I.S.C. (art. 571(1)), and the right to establish it lapses 5 years after the act (para. (2)). The text requires the reception to be admitted, so a report recording a rejected reception does not give you the right to move in. The utility condition is part of the same letters: letter (l) speaks of authorised, permanent connections, and letter (m) of connections that have been received, in line with the suppliers’ approvals attached to the permit. Site power does not stand in for them.

Building tax does not wait for the report

Many owners put off reception in the belief that, without it, the house never reaches the tax office. That was not true before 2026 either, because the date of acquisition does not wait for the report (see below). Since 25 February 2026 the town hall also has a route of its own: Emergency Ordinance 7/2026 added paragraph (1^1) to article 461 of the Fiscal Code. Building tax is also due for a building whose permit is still valid if the town hall’s authorised staff find, by 31 December of the previous year inclusive, that it is finished or in use, even though no reception report has been drawn up. Letter (b) of the same paragraph does the same for a building put up without a permit.

The rest of article 461 sets the deadlines. For a new building finished before its permit expires, the date of acquisition is the date of the reception report, but no later than 15 days after the works were actually finished (para. (3)(a)). The declaration to the local tax office is due within 30 days of acquisition (para. (2)). If you do not file it, the tax set by the town hall rises by 30% for each six-month interval of delay, or part of one (para. (4)). A house nobody declared therefore pays the same tax, with a surcharge.

The permit clock keeps running

A building permit carries an execution period, and the Code says what happens at its end: permits lapse when the works are not finished within the execution period set in the permit, unless an extension of that period was requested (art. 310(2)). If the works are not finished while the permit is valid, paragraph (6) requires a new permit. The extension is granted once, for at most 12 months.

The application, fee and deadlines for the extension are on the page about extending a building permit.

From here on this is our reading, not a written rule. Article 280(1) includes reception in the definition of completion, and article 310(2) penalises works that are not completed. Read together, the two suggest that a house that is physically ready but not received when the execution period ends risks being treated as unfinished. There are arguments the other way. Annex 1 defines an unfinished building (construcție nefinalizată) as one whose completion still involves work left to do, physically and in value, and a finished house has nothing left to build. The Fiscal Code also provides for buildings finished by the permit’s term, with the reception report to be drawn up within the legal deadline (art. 461(3)(b)). The Urbanism Code does not say what happens to a reception called after the execution period has ended, so if the deadline is close, ask for the extension, or for a written answer from the issuing authority, before it expires, not after.

The Fiscal Code also covers the case where the period expired by 31 December of the previous year, with no extension and without notifying the issuing authority that the works could not be finished in time, and the house is not finished: tax is set on the floor area that has walls and a roof, based on a partial reception report that must be drawn up on the date the permit expires. If you built it yourself (în regie proprie), you must notify the town hall so that it can take part in that partial reception (art. 461(3)(c)).

The money that closes at reception

Between the end of the works and reception (the Code calls it the completion date), the applicant settles with the issuing authority the value of the authorised works and the statutory levies (art. 280(9)). The balance of the 0.5% levy paid to I.S.C. is due no later than the date the reception report is signed (art. 352(2)(b)), and late payment carries a penalty of 0.15% a day (para. (3)). Separately, the Fiscal Code requires a declaration of the value of the works within 15 days of completion, but no later than 15 days after the permit expires (art. 474(7)(c)).

How the two instalments to I.S.C. are worked out is in the 0.5% I.S.C. levy.

A late reception: what to prepare

While the permit is valid, a late reception follows the same rules as one held on time. Reception is carried out by the owner or the developer (art. 527(2)); for a developer, the Code requires it to be organised on the contractor’s notice and completed within 30 days (art. 423(7)(a)). For a house with a building permit, the reception committee must include a representative of the authority that issued the permit (art. 280(3)). For works carried out under a notification, reception takes place between the contractor, the owner and a representative of the local authority, and a copy of the report is registered in the National Register of Buildings, or sent to I.S.C. while the register is not yet operating (art. 298(6)).

The reception file has its own list in article 528(3): the designers’ and the site supervisor’s statements, the reception reports, the building’s technical book, the use and maintenance manual, the training sheets and the as built design. A new house also needs its energy performance certificate, without which the report is void. The reception regulation in HG 273/1994 stays in force under article 577(6) until it is amended; the procedure itself is on the page about reception at completion of works.

One obstacle is not solved by waiting. Buildings put up without a permit, or departing from it, cannot be received (art. 280(8)). For a departure already built, the amendment permit no longer helps: it is requested before the modification works and only while the building permit is valid (art. 293(2)-(3)). What was built differently from the permit needs a regularisation permit (art. 301(1)), which is issued only for certain buildings and floor areas (para. (2)) or, until around 25 August 2027, for other buildings too, at ten times the levies and fees (paras. (7)-(8)). Reception comes after it.

Where to start if you are already late

The tax declaration does not wait for reception, so it comes first. The other steps depend on each other.

  1. Declare the building to the local tax office, if you have not. For a house finished before the term in its permit, the date of acquisition is the date of the reception report, but no later than 15 days after the works actually ended (Fiscal Code, art. 461(3)(a)), and the declaration is due within 30 days of the date of acquisition (para. (2)). For a house finished long ago that deadline has passed, and the surcharge grows with every six months.
  2. Check the date on your permit. If the execution period ends soon, ask for the extension at least 15 working days before (art. 310(5); art. 309(6) says only 15 days, so count working days). If it has already ended, ask the issuing authority in writing how reception can still be held before you call it. If you built something other than what the permit allows, regularisation comes first. Then, with the art. 528(3) file and the energy certificate together, you call the reception. With the report in hand, for a house with a building permit, you apply for the certificate attesting the building, the document the land registration rests on. Works under a notification are registered another way (art. 298(7)).

This article is analysis, not legal advice. The provisions cited are from Legea 169/2026, published in Monitorul Oficial no. 661 of 10 August 2026, from the Fiscal Code (Law 227/2015) and from Law 7/1996, in the consolidated versions consulted on 21 October 2026. The content of HG 273/1994 was not checked. Romanian legal terms are kept in the original where the translation would lose precision. Check your own situation with the issuing authority.

AutoRize Team

The AutoRize team

We write about construction permitting in Romania: what has changed, what it means for your file and what to do now.