Critical phases (faze determinante): the report and the ISC

A critical phase stops the works until the client, the designer and the contractor sign. When the ISC attends, who convenes, what changes for a rural CC1 house.

Citește în română

A critical phase (fază determinantă) is a point in the works at which building stops until the client (beneficiar), the designer and the contractor give their written consent to continue. That is how the Urbanism Code defines it (Legea 169/2026, Annex 1), and the phases are set by the designer in the inspection programme (programul de control) that is part of the project. The State Construction Inspectorate (ISC) does not appear in that definition. It authorises continuing the works at the phases for structural strength and stability, but only on buildings under its control. The Code takes CC1 houses in villages out of that control (art. 466(5)).

What a critical phase is

Annex 1 to the Code defines it as the physical stage, set by the designer in the inspection programme, at which works, once reached, cannot continue without the written consent of the client, the designer and the contractor. The inspection programme is the part of the project that fixes the inspection stages by field and category of works, including these phases. The Code does not list the phases: your project gives the list, and on buildings under state control the inspectorate can change it.

WhoWhat they do at each phaseWhere it is written
The designerSets the phases in the inspection programme and takes part in checking themLaw 169/2026, Annex 1; art. 426(1)(f) and (k); art. 520(3)(c)
The contractorConvenes the participants and provides the conditions for the checkart. 452(3)(e); art. 520(4)(a)
The site supervisor and the contractor’s technical managerTake part directly in the checkart. 456(1)(b); art. 459(1)(d)
The clientGives written consent, together with the designer and the contractorAnnex 1
The ISC, through the county inspectorateAuthorises continuing at the phases for structural strength and stability, on buildings under state controlart. 520(4)(b); art. 466(5)

The Code also requires the phases in the contract: the specific clauses of the works contract include them (art. 408(4)(f)).

Who convenes and who signs

The contractor convenes the participants set in the quality assurance programme for these phases and prepares the conditions for the check, to obtain their consent to continue (art. 520(4)(a)). That programme is drawn up by the structural design engineer (art. 430(8)(e)). The site supervisor (diriginte de șantier) and the contractor’s technical manager (responsabil tehnic cu execuția, RTE) take part directly in the check (art. 456(1)(b), art. 459(1)(d)). The written consent to continue is given by the client, the designer and the contractor (Annex 1), and designers sign the reports for these phases only after the site supervisor and the technical manager (art. 426(3)).

The roles of those two are covered in the site supervisor and the RTE.

The Code fines two failures: a contractor that does not convene the participants or provide the conditions for the check, and a convened participant who stays away without good reason (art. 570(1)(ii) and (jj)). For each, the fine runs from 10,000 to 20,000 lei and a warning alone is not possible (para. (2)(c) and para. (3)). The same range covers a designer who does not set the phases (para. (1)(ff)).

When the ISC attends and when it does not

The ISC attends the phases for structural strength and stability, and only on buildings under state control. There, continuing the works is authorised by the representative of the county construction inspectorate or the Bucharest one. Authorisation comes after the designer, the contractor and the client have carried out the checks in the inspection programme and the quality plan and drawn up the quality documents for the materials, for the works that become hidden and for the remedied defects (art. 520(4)(b)). The state control regulation, approved by HG 492/2018 and still in force (art. 577(7)), describes these checks on the basis of the programmes approved by the county inspectorate (art. 7(c)).

Not every building is under ISC control, though. The Code excludes CC1 buildings located in rural areas and in villages belonging to municipalities and towns, temporary buildings, and works that can be done without a permit (art. 466(5)). These fall under the control of the local authorities. The 2018 regulation has a narrower exception: only single-storey (ground floor) single-family homes and farm outbuildings owned by individuals, in villages (art. 3(1)). Our reading is that the Code’s wider exception prevails, and that for a CC1 house in a village the phases in the project remain, with the written consent of the client, the designer and the contractor, but with no ISC representative at the check.

How to find your house’s class is explained in the consequence class.

The report and the ISC procedure

On buildings under state control, the findings go into the phase report, on the template in ISC procedure PCF 002, approved by Order 1370/2014. The procedure predates the Code and refers to Legea 10/1995, most of which the Code repealed (art. 576(3)(c)). The Code requires the authorities that issue opinions (avize), agreements and permits to update their procedures issued under Legea 10/1995 within 120 days of the Code’s publication, that is by around 8 December 2026 (art. 583(4)). On our reading, this deadline covers this procedure too. For now, the published procedure says:

  • the county inspectorate approves the inspection programme, may ask for the number and type of phases to be changed, up or down, and may set phases on its own initiative (art. 9(2)(c));
  • the contractor sends the convocation to the inspectorate at least 3 working days in advance (art. 15);
  • if the inspectorate cannot send a representative, it tells the applicant in writing, noting that the approved programme is changed (art. 9(3)(a));
  • the findings go into the phase inspection report, and the inspector decides whether to authorise continuing (art. 9(3)(c));
  • the report comes with copies of the drawings signed by the site supervisor and with photographs showing the date and time (art. 11).

The procedure gives templates for the convocation, the notice and the report in annexes 1-3. In our reading, a phase report without the ISC is normal in two situations: the building is not under state control, or the inspectorate has said in writing that it will not attend. What follows the last phase is on the page about reception at completion of works.

What to track on site

  1. Ask the designer for the inspection programme and the list of critical phases.
  2. Check the contract with the contractor for the clause on the phases.
  3. Find out the consequence class and whether the plot is in a village, so you know whether the ISC comes.
  4. At each phase, make sure the contractor has convened all participants in time.
  5. Keep the signed reports, with the drawings and photographs, until the reception.

This article is analysis, not legal advice. The provisions cited are from Legea 169/2026, published in Monitorul Oficial no. 661 of 10 August 2026, from the regulation approved by HG 492/2018 and from the ISC procedure PCF 002 (Order 1370/2014), which predates the Code. Romanian legal terms are kept in the original where the English would be misleading. Check your own situation with the issuing authority.

AutoRize Team

The AutoRize team

We write about construction permitting in Romania: what has changed, what it means for your file and what to do now.

Your certificat de urbanism file, in 30 seconds

AutoRize generates the application, the memoriu de prezentare and the opis for the certificat de urbanism, matched to local planning rules.

Get started