Apartment walls: what you can knock down unpermitted

Only finishes, joinery and services need no paperwork. A light partition goes on notification, masonry is unclear, a load-bearing wall needs a permit.

Citește în română

Most guides to knocking down a wall in an apartment still describe Legea 50/1991, repealed on 25 August 2026. The Urban Planning Code (Legea 169/2026) gives one clear exception for walls: a non-structural, demountable partition made of light materials. A masonry wall that does not hold the building up is not clearly named on any list. A load-bearing one is a change to the structure, so it needs a permit. The word load-bearing has no definition in annex 1 of the Code, the one with the terms. It takes an engineer, not the text of the law, to decide what kind of wall you have.

The answer, by situation

What you doRegimeWhere it says so
Repair or replace interior joinery, plaster, paint, tiling, floors, interior servicesNo permit and no notification, outside protected built-up zones and monument protection zonesart. 299 para. (2) lit. a) pts. 3, 7, 9
Move or remove a non-structural, demountable partition made of light materialsNotification, if you do not affect escape routes, fire-safety installations and fire resistance; outside protected built-up zones and monument protection zonesart. 294 para. (2) lit. b) pt. (viii)
Renovate or extend the kitchen or bathroom of a block apartmentNotificationart. 294 para. (2) lit. b) pt. (iv)
Knock down a non-structural masonry wallNot clearly on any list; our reading: permitart. 259 para. (6)
Knock down or open a load-bearing wall, or you do not know which kind it isBuilding permit for intervention works; if you do not know which kind of wall it is, an engineer classifies it firstart. 259 para. (2) lit. b), para. (3)
The wall was knocked down without papersPermanent regularisation does not cover the inside of an apartment; the temporary window remainsart. 301 para. (2), (7)

What needs nothing: finishes, joinery, services

Article 299 paragraph (2) letter a) lists the works on existing buildings that you can do with no formality at all, with a condition stated at the start: the building is not in a protected built-up zone or in a monument’s protection zone. Three points matter for the interior of an apartment: repairs and replacement of interior joinery (point 3), of plaster, paint, tiling, finishes and interior floors (point 7), and repairs or replacement of interior services (point 9).

Point 10 adds local heating systems and individual air conditioning, which we covered separately in boiler and air conditioning: what the law asks.

None of these points mentions walls. A wall that disappears is not a finish, not joinery and not a service, so the list does not cover you.

Having no formalities does not remove the rules. Paragraph (3) keeps the duty to respect the technical rules on quality in construction, paragraph (4) puts liability on the beneficiary, jointly with designers and contractors, and paragraph (5) requires a reception on completion, entered with the execution design in the building’s technical record and in the National Register of Constructions. Read literally, paragraph (5) applies to every work on the no-formality list, painting included; how councils apply that to small jobs we have not seen documented.

A light partition goes on notification

Article 294 paragraph (2) letter b) point (viii) allows on notification changes to interior compartmentation that are non-structural, demountable and made of light materials, only if they do not affect the length or clearance of escape routes, the working of installations that ensure fire safety, or the fire-resistance grade or fire-stability level of the building. Again, outside protected built-up zones and monument protection zones.

The Code defines neither demountable, nor light materials, nor compartmentation: we searched annex 1 for the terms and they are not there. Read plainly, the text describes plasterboard on a metal frame or prefabricated panels, which come apart without leaving a ruin behind. A wall of aerated concrete or brick does not come apart, it is demolished, so point (viii) no longer seems to cover it. Nobody says clearly where the line is, and a light partition that also serves as a fire-protection wall no longer passes the third condition. What a fire-safety scenario asks of a lived-in space we explained in the fire-safety scenario at permit stage, and the page on the ISU fire-safety approval shows when it is required.

Point (v) of the same letter, with remodelling of non-structural interior walls, ends with if the size of the house is not changed, for single-family homes. Our reading is that it is written for houses and does not reach an apartment in a block. If the sentence is read the other way, with single-family homes tied only to the size condition, the point would cover non-structural walls in any building, a masonry wall in an apartment included, again on notification. For the kitchen and bathroom there is point (iv): renovation and extension of the kitchen, renovation and extension of the bathroom, in apartments of collective housing. The point does not say what kind of wall you may move for the extension, so if the kitchen grows at the expense of a masonry or load-bearing wall, it is not certain that (iv) covers you.

The notification is filed on form F_NOT_01 of Order 975/2026, with an execution design with simplified content, drawn up by architects and engineers (article 295 paragraph (4)). The council has at most 15 working days to ask for clarifications, tell you the work needs a permit, or reject the notification; if it does nothing, tacit approval takes effect when the 15 days run out (article 296 paragraph (1)). Work may start 15 calendar days after that deadline (paragraph (6)) and you have 3 years to carry it out (paragraph (5)). The steps and the fee are on the page about the simplified notification, and the step-by-step eligibility check is in do you qualify for the notification.

Non-structural masonry: no clear list

The brick partition between kitchen and living room, which everyone knows as “not load-bearing”, is the case without a text. The no-formality list (article 299) does not contain it. The notification list asks for compartmentation that is demountable and made of light materials, and the point for non-structural walls, (v), is, on our reading, written for houses. What remains is the general rule of article 259 paragraph (6): a building permit is issued mandatorily for all works in paragraph (2), except those that go on notification or with no formality. Paragraph (3) includes, among intervention works, modification and partial demolition.

So our reading is that knocking down a masonry wall, even a non-structural one, needs a permit. It is not a certainty: the Code nowhere says the non-structural brick wall needs a permit, and a council may classify it differently; if point (v) is read broadly, such a wall would go on notification. You can ask in writing beforehand. Article 295 paragraph (9) states that a request to classify a work under an authorisation regime is not a notification and is settled under ordinary law, so the question does not start the 15-day clock.

The load-bearing wall: permit, design and expert report

For a wall that carries the structure there is no exception. It is an intervention on an existing building, with a building permit (article 259 paragraph (2) letter b), paragraph (3)). The design for intervention works contains the pieces of the ordinary design and, as the case may be, the detailed survey and the technical expert report or technical note of an attested expert (article 282 paragraph (1)). The technical expert report is, however, mandatory for substantiating the design of interventions on existing buildings and for assessing the influence of an intervention, demolition included, on neighbouring properties (article 437 paragraph (2) letters a) and d)); article 285 paragraph (2) bases intervention works on expert reports by attested experts. Paragraph (1) of the same article allows self-build only for maintenance and current repairs, so a structural intervention is not something you can do yourself. When you do not know whether the wall is load-bearing, a structural engineer’s calculation is the only way to know what to ask for.

How the survey is done is in the survey of the existing building, and when an expert report is needed in technical expert report for existing buildings.

For interventions made exclusively inside, article 282 paragraph (2) requires the design to be done by architects or interior architects with a right to sign, together with structural and services engineers and, as the case may be, engineers from other fields. Who answers for what in the design is explained in who signs the design.

In a block, the civil side comes in too. The Civil Code lists the structure, the load-bearing structure and the perimeter and dividing walls between properties and/or common spaces among the common parts of the building, unless the law or the legal act provides otherwise (article 649 paragraph (1) letter b)). The Urban Planning Code requires the consent of neighbours or of the homeowners’ association, in authentic form, at article 261, only when the work needs measures to secure existing buildings identified by a technical expert report. What the homeowners’ associations law or the block’s rules require in addition we have not analysed here; ask the administrator before calling the crew.

In a protected zone

The no-formality list and notification point (viii) start with the same condition: outside protected built-up zones and monument protection zones. The one opening is article 274(6): in a protected built-up zone, though not in a monument protection zone, works without any formality are allowed only where the local urban planning regulation provides for it. The Code does not say how this squares with the condition at the start of the list, so our reading is that you should ask the town hall first. For buildings in these zones that are not listed monuments or monuments in the process of listing and have no architectural or historic value set by urban planning documents, article 294 paragraph (3) has its own list, on a notification also sent to the local culture department, with its written agreement. On it are non-structural, demountable partitions of light materials, if they do not change the interior spatial concept (letter g)), but not structural changes.

Which approvals are collected there is in what approvals a protected zone requires. Works done without a permit in such a zone are a crime, with imprisonment from 3 months to a year or a fine (article 356 paragraph (1) letter a)).

If the wall is already down

The permanent regularisation permit can be issued only for single-family houses of at most 150 sq m developed area, for annexes and for balcony enclosures (article 301 paragraph (2)). The inside of an apartment is not on the list. What remains is the temporary exception in paragraph (7), which targets other categories of constructions for at most one year from the Code’s entry into force, so until around 25 August 2027, with quotas and fees ten times higher (paragraph (8)) and with technical expert reports on the fundamental requirements (paragraph (9)).

At length in the one-year window for regularisation. If the cumulative conditions in paragraphs (3) and (4) are not met, paragraph (5) points to the legal measures for removing the works; where technical solutions exist, paragraph (6) lets the council require a building permit or a partial-demolition permit.

The penalty for executing without the required permit is a fine of 50,000 to 1,000,000 lei; without the required notification, 5,000 to 50,000 lei (article 357 paragraph (1) letters a) and b), paragraph (4) letters a) and b)). Details are on the page about fines for building without a permit.

Tenants and the owner’s wall

If you are not the owner, article 245 paragraph (4) letter a) lets you, on the basis of a claim right, carry out repairs to permanent buildings and interior compartmentation that is non-structural and demountable, with the owner’s agreement. The notification can also be completed by the holder of a claim right (article 295 paragraph (2)); for masonry or structure the decision stays with the owner, and article 245 paragraph (4) does not cover it.

The question to ask before you touch the wall

The question is not whether the wall “can be knocked down” but what it is made of and what it holds up. If the answer is plasterboard and you do not touch the escape route, you are talking about a notification. If it is masonry, you write to the council and start from the idea of a permit. If nobody knows, you pay for the expert report first, not the hammer.


This article is analysis, not legal advice. The provisions cited are from Legea 169/2026, published in Monitorul Oficial no. 661 of 10 August 2026, and from the Civil Code (Legea 287/2009). Check your own situation with the issuing authority.

AutoRize Team

The AutoRize team

We write about construction permitting in Romania: what has changed, what it means for your file and what to do now.

Your certificat de urbanism file, in 30 seconds

AutoRize generates the application, the memoriu de prezentare and the opis for the certificat de urbanism, matched to local planning rules.

Get started