Old house demolished without a permit: what follows

An old house is demolished on a permit. Without one, the fine starts at 50,000 lei, and at a monument or in a protected zone the act is a crime.

Citește în română

To demolish an old house you need a permit. Without one, the demolition is a contravention, and at a monument or in a protected zone it becomes a crime. The Urban Planning Code (Legea 169/2026) says what is sanctioned, but not how a demolition already carried out is put right. Below are the fines, the cases that go on notification and the rule for a new house in place of the old one.

In short: which act you need and what fine you risk

CaseWhat the Code requiresWhere it says so
You demolish the house and want to build in its placeA single building permit that covers both works; only the fee for the new construction is paid (exception: a new house that can go on notification, art. 294 para. (2) lit. a) pt. (ii))art. 302 para. (2)-(3), art. 248 para. (3)
You demolish the house and build nothingDemolition permit, issued on the same conditions as a building permitart. 302 para. (1), art. 246 para. (2)
You demolish a farm outbuilding or a construction outside a single-family home, outside protected built-up zonesNotificationart. 302 para. (5)
You demolished without the required permitContravention, 50,000 to 1,000,000 leiart. 357 para. (1) lit. b), para. (4) lit. b)
The same act, seen as demolition in breach of the authorisation rulesContravention, 50,000 to 100,000 lei, recorded by the State Inspectorate in Construction (I.S.C.); the Code does not say which of art. 357 and art. 570 appliesart. 570 para. (1) lit. a), para. (2) lit. a), art. 571
You demolished without the required notification (outbuildings)Contravention, 5,000 to 50,000 leiart. 357 para. (1) lit. a), para. (4) lit. a)
You started demolishing without an execution design that has been drawn up and verifiedContravention, 5,000 to 30,000 leiart. 357 para. (1) lit. r), para. (4) lit. i)
The property is a monument, is in a monument’s protection zone or in a protected built-up zone, or has special architectural or historic value set by approved urban planning documentsCrime, 3 months to a year of imprisonment or a fineart. 356 para. (1) lit. a)
You want to regularise the demolitionThe Code has no route for this; our readingart. 301 para. (1)-(2), (7), art. 358 para. (1)

Which act you need to demolish the house

The house itself is demolished on a permit. That is a demolition permit if you only pull it down, or a building permit if you put up another in its place under a building permit. The demolition permit allows the demolition, decommissioning or dismantling, partial or total, of constructions (article 246). It is issued on the same conditions as the building permit (article 302). Partial demolition is also listed among intervention works (article 259). The house is not on the notification lists, set out in the next section.

The design for authorising a demolition (PAD) has the content set out in annex 5 of the Code (article 302). What the file contains and how to request it is on the page about the demolition permit. The move from the old DTAD to PAD is in DTAD is now PAD.

When you do not need a demolition permit

Farm outbuildings, constructions outside a single-family home and an old fence you are replacing can be demolished on notification instead of a permit, under certain conditions. The notification is still required. Farm outbuildings and constructions outside single-family homes are demolished on notification if they are outside protected built-up zones (article 302). New fences built by removing old ones also go on notification, outside protected built-up zones and monument protection zones, under the urban planning rules (article 294).

Nor do you, as a rule, need a separate demolition permit when you demolish the house to build another. The demolition goes into the building permit for the new house, and only the fee for the new construction is paid (article 302). How the permit fees are worked out is on the page permit fee calculation.

Demolition and a new house: one permit

If you want a new house in place of the old one, the authority issues a single building permit. It approves both the demolition of the old construction and the building of the new one (article 302). The rule is general: a project combining new works with interventions or demolitions needs a single building permit, which shows the categories of authorised works separately (article 248).

The exception is a new house that can go on notification, under the narrow conditions of article 294. The Code then does not say on which act the old house is demolished, and it is not on the notification list in article 302. Our reading is that the demolition permit remains.

The application for the urban planning certificate for new constructions, landscaping works and extensions is accompanied, among other things, by the proposed site plan. It shows the ground footprint of the buildings that are to be demolished, built or extended (article 257). The old house therefore appears in the file as a building that is to disappear.

If you rebuild the house keeping the same function, the same ground footprint and the same volume, you do not need new urban planning documentation (article 252). The article does not say which act the work needs; for a whole house, our reading is that it remains a permit. Reconstruction means rebuilding, on the same site, an existing construction too deteriorated to be strengthened or restored, or on which the works would cost too much (article 372).

The old house is already down: the fines

Demolishing without the required permit is fined 50,000 to 1,000,000 lei, and without the required notification, 5,000 to 50,000 lei. Starting a demolition without a technical execution design, drawn up and verified, is a further contravention, fined 5,000 to 30,000 lei (all three in article 357). I.S.C. can record and sanction any of them, and the control departments of the local authority only the first two.

Article 570 also sanctions building or demolishing in breach of the provisions on authorisation and execution, with a fine of 50,000 to 100,000 lei imposed by I.S.C. The right to impose it lapses 5 years after the act (article 571). The Code does not say how to choose, for a particular demolition, between article 357 and article 570.

The Code’s sanctions (the fines above and the offence in article 356) apply to demolitions carried out from 25 August 2026. For one carried out earlier, the law at the time of the act, Legea 50/1991, generally applies. The new law applies only if it is more favourable (article 15 paragraph (2) of the Constitution).

For the fine in article 357 we found no limitation period of its own. Paragraph (7) ties a period to the completion in fact of a finished construction, but points to paragraph (5), which contains none. Nor does the general period in Government Ordinance 2/2001 fill the gap, as we first wrote here. The Code excludes the ordinance, with the exceptions in articles 144 and 571 (article 581). In detail: does unpermitted construction time out?. How a report leads to an inspection we explained in reporting a building without a permit.

Regularisation after a demolition

The regularisation permit exists only for constructions that stay. Hence our reading: the Code offers no way to legalise a demolition afterwards, and it does not undo one; the fine remains.

After the fine, the control body must order measures. Those in article 358 concern bringing the works into line with the permit, obtaining a regularisation permit or demolishing works done without a permit. None concerns restoring a demolished building. Regularisation is granted only for single-family homes of ground floor or ground floor plus one storey, up to 150 sq m developed area, for outbuildings and for balcony enclosures (article 301). The temporary exception in the same article also concerns constructions.

Nor does the Code say what happens to the right to rebuild the demolished house to the same dimensions. Article 372 adds to reconstruction the rebuilding, from measured surveys, visual archives and images, of constructions of historic, cultural or architectural value that have vanished or been damaged. For an ordinary house, our reading is that a vanished building is hardly still an existing construction in the sense of annex 1 of the Code, the one with the definitions. And the old dimensions must be proved from documents made earlier, for example an older survey and the land register extract. How the survey of a building that is still standing is done is in the measured survey.

Demolition waste

Demolition works also need a waste management plan. The holder of the building or demolition permit, or the beneficiary of works on notification, must have one (article 394). The Code does not say who carries that duty for a demolition done with neither a permit nor a notification. It does put responsibility for waste management on the developer, the producer and the contractor.

Who pays for the waste is in construction waste: who pays for it.

At a monument or in a protected zone

Here a demolition without a permit becomes a crime, punished with imprisonment from 3 months to a year or a fine (article 356). The rule covers historic monuments and their outbuildings in the same property, their protection zone, protected built-up zones and constructions of special architectural or historic value set by approved urban planning documents.

Interventions on properties in protected zones are made only on the prior approval or consent of the Ministry of Culture or its local departments and of the environmental authority (article 190). Article 274 requires the Ministry of Culture’s approval for demolition too, as the law provides, and article 284 does so when the situation requires it.

An old house in the centre of a town or village, or next to a church, may well be in such a zone. The urban planning certificate tells you whether it is. The approvals gathered there are in what approvals a protected zone needs, and for the neighbourhood of a monument, in a house in a historic monument’s protection zone.

Before any machine comes on site

The demolition comes last, after the paperwork. The order is:

  1. The urban planning certificate, with the purpose set by what you want to do on the land: demolition, building or both.
  2. The permit: a demolition permit if you only demolish, or a single building permit if you put something in the house’s place, plus the approvals the certificate asks for.
  3. The waste plan.
  4. The demolition.

Whoever demolishes first is left with a fine for the demolition. On a plot where the old house no longer exists, they then have a building permit to request, or a notification, if article 294 allows it.


This article is analysis, not legal advice. The provisions cited are from Legea 169/2026, published in Monitorul Oficial no. 661 of 10 August 2026. Check your own situation with the issuing authority.

AutoRize Team

The AutoRize team

We write about construction permitting in Romania: what has changed, what it means for your file and what to do now.

Your certificat de urbanism file, in 30 seconds

AutoRize generates the application, the memoriu de prezentare and the opis for the certificat de urbanism, matched to local planning rules.

Get started