Solar panels on a house: prior notice, not a permit

A prosumer can fit solar panels on a house, outbuilding or the ground without a permit, but with prior notice to the town hall. Who it covers and what stays.

Citește în română

The first results for solar panel permit Romania are installation firms and forums, and the answers contradict each other: some say nothing is needed, others say a permit is. The Urbanism Code (Legea 169/2026) has a point written for exactly this, and it gives neither answer. A prosumer’s panels are fitted without a building permit, but not with nothing: the town hall must be notified beforehand.

Romanian terms are kept in the original: înștiințare is a prior notice, notificare is the simplified procedure of art. 294, and a prosumator is an owner who both consumes and produces power.

What point 13 says

It is article 299 para. (2) letter a) point 13, in the list of works that can be done with no formality. The text brings several conditions together, all cumulative:

ElementWhat it says
WhoOwners of properties who are prosumers, as defined by art. 3 point 95 of Legea 123/2012
WhatPhotovoltaic systems producing electricity and/or solar panels for heating or hot water for own consumption
WhereOn buildings, on household outbuildings (see the household outbuilding) and on the ground
The formalityPrior notice (înștiințare) to the local public authorities
The structureThe system sits on structural elements that ensure the stability of the whole and carry its own weight, wind and snow

The point also says the work must comply with the legislation in force, so nothing below takes the installation outside the other rules.

A prior notice is still a formality

The article is titled works carried out with no formality at all, yet point 13 asks for prior notice. The two do not fit together strictly, but the text is clear at the level of the point: you notify the town hall before you start. The point does not name a form, does not set a waiting period and does not require an answer from the town hall. It is not the simplified notificare of art. 294, with a technical project and 15 working days for tacit approval; for the notificare the procedure is different.

What to do in practice: send the notice in writing or digitally, keep proof of registration and do not start installing before you have it. Without it you risk at least the offence in art. 357 para. (1) lit. d), failing to give prior notice of works that need no permit, fined 50,000 to 100,000 lei (para. (4) lit. d)). On our reading, the council could also argue that the works fell outside point 13 and needed a building permit (art. 259 para. 6).

When point 13 does not apply

  • You are not a prosumer in the sense of the energy law. The point is written for owners who are prosumers. A plant that sells power as a business is not described there.
  • The property is in a protected built area or a monument protection zone. Letter a) opens with outside protected built areas, so all its points, the 13th included, are limited by it. The one opening is article 274(6): in a protected built-up zone, though not in a monument protection zone, works without any formality are allowed only where the local urban planning regulation provides for it. The Code does not say how this squares with the condition at the start of the list, so our reading is that you should ask the town hall first. The list in art. 294 para. (3), the one for protected zones, does not mention panels. Read about the regime of the zone in a house in a monument protection zone.
  • The work touches the roof as well. If the job also means changing the roof, the roof rules add up; we covered them in roof, windows, facade.

In a block of flats, the text does not answer everything

Point 13 speaks of property owners without telling a house from an apartment. It says nothing about the other owners’ agreement and is not where it is decided who may use the shared roof: that belongs to shared property, not to urbanism. The notice to the town hall does not replace that discussion. Grid connection as a prosumer is a separate procedure, with the network operator, under the energy rules.

No formalities does not mean no rules

Paragraphs (3)-(5) of art. 299 apply here too. Compliance with urbanism and technical rules is mandatory, liability for breaching them falls on the beneficiary jointly with the designers and contractors, and acceptance at completion is mandatory and is entered in the building’s technical record and in the National Register of Constructions. The text does not say who certifies the support structure; it says only that it must be able to carry the loads. Ask the installer for a contract and an acceptance record, not only an invoice.

The full list of works that go without a permit is on the page about works without a building permit. If your installation does not fit point 13, the route is the building permit, with the urbanism certificate first.


This article is analysis, not legal advice. The provisions cited are from Legea 169/2026, published in Monitorul Oficial no. 661 of 10 August 2026. Check your own situation with the issuing authority.

AutoRize Team

The AutoRize team

We write about construction permitting in Romania: what has changed, what it means for your file and what to do now.

Your certificat de urbanism file, in 30 seconds

AutoRize generates the application, the memoriu de prezentare and the opis for the certificat de urbanism, matched to local planning rules.

Get started