Almost every contract de antrepriză template circulating for a house was written before August 2026. That does not make them wrong, because their civil-law part has not changed. What has changed is the special law the Civil Code points to for defects, and there the Urbanism Code (Legea 169/2026) has an article no old template cites.
So the contract rests on two texts. The Civil Code (Law 287/2009) governs the works contract in articles 1,851-1,873 and, separately, the works contract for construction in articles 1,874-1,880. The Urbanism Code sets the contractors’ liability in article 451.
When it is a construction works contract
Article 1,874 defines it through the permit: a contract under which the contractor undertakes to carry out works that, by law, require a building permit. A fence or a repair done without a permit falls under the general rules of the works contract, not the special ones.
Article 1,855 draws the line with a sale. If, by the parties’ intention, carrying out the work is not the main purpose of the contract, the contract is a sale. Someone buying a finished house from a developer is not entering a works contract, and other rules apply there, which we covered in buying from a developer.
The permit is your obligation
Article 1,875 paragraph (2) puts obtaining every authorisation the law requires on the owner. The contractor only has a duty to cooperate: it gives you the information it has, or should have given its specialisation. A contract in which the firm also handles the paperwork can move the work, but towards the authority the application and the obligation stay yours. What the permit file contains is on the building permit page.
The same article, in paragraph (1), requires you to allow the use of access routes, water and the property’s other utilities, to the extent the work needs them.
The price: estimated or fixed
The difference between the two decides who pays for surprises.
| Price type | The rule | Article |
|---|---|---|
| Estimated | The contractor must justify any increase, and you pay it only if it comes from work that could not have been foreseen by the contractor at signing | 1,865 |
| Based on the value of the work | On request, the contractor accounts for progress, services and expenses | 1,866 |
| Fixed (lump sum) | You cannot ask for a reduction because it cost less, and the contractor cannot ask for more because it cost more | 1,867 para. (1)-(2) |
Paragraph (3) of article 1,867 is the one that matters for a house: a fixed price stays unchanged even if the original conditions of execution were modified, unless the parties agreed otherwise. Anyone who changes the design along the way and wants a different price has to write it into the contract. How the budget splits by stage is in budget margin by stage.
If the contract has no price, article 1,854 paragraph (3) points to the price set by law, and failing that to a price set by the work done, the necessary expenses and custom.
Payment on acceptance, unless you write otherwise
The default rule, in article 1,864 paragraph (1), is that the price is paid at the date and place of acceptance of the whole work. Stage payments, advances and retentions exist if the contract (or, rarely, the law) provides for them.
The contractor, on the other hand, has a security it does not need to negotiate: article 1,869 gives it a legal mortgage over the work for the price owed, created and preserved under the law.
Checking the work and works that get covered up
You may check progress, quality, the appearance of the work and the materials, without disrupting the contractor’s normal activity (article 1,876 paragraph (1)). Findings and instructions are communicated in writing, unless agreed otherwise (paragraph (2)).
Paragraph (3) is the most practical rule in the whole chapter. When a part of the work that will be covered by later work is finished, such as reinforcement before the pour or services before plastering, the contractor and the owner jointly record that it exists and complies. The contractor summons you to the site, and if you do not turn up on the date communicated, it may draw up the record alone. After that, there is nothing left to check by eye.
If the contractor finds errors or gaps in the design, article 1,877 requires it to tell you and the designer straight away, with proposed fixes. If you take no measures, with the designer’s opinion, or the measures are inadequate, it may suspend the works.
Subcontractors and their workers
The contractor may hand parts of the work to subcontractors, unless the contract was concluded because of who the contractor is, and it answers to you for them as for its own acts (article 1,852).
Less known is article 1,856. People who worked under a contract with the contractor and were not paid by it have a direct claim against you, up to the amount you still owe the contractor when the claim is brought. That is why a careful owner ties each payment to an accepted stage, not to the calendar.
Acceptance moves the risk
Article 1,878 refers to the acceptance the law provides for: first acceptance on completion of the works, then final acceptance. Risk passes to you from the date of acceptance on completion (paragraph (2)). Until then, if the work perishes or deteriorates for reasons not attributable to you, the contractor who supplied the material redoes it at its own cost (article 1,860).
Accepting without reservations has a cost. Under article 1,862 paragraph (3), an owner who accepted the work without reservations can no longer rely on apparent defects. What happens at the acceptance committee and what documents are handed over is on the acceptance on completion page; the case of a house built without a contractor is in accepting a self-built house.
Defects: where the Urbanism Code comes in
Article 1,879 paragraph (1) of the Civil Code gives no warranty periods. It says they are those set by the special law. The special law is now the Urbanism Code, and its article 451 says three things worth keeping in mind when you read a contract:
- Contract terms cannot set liabilities below the legal ones (paragraph (2)). A clause that cuts liability below the law does not have the effect its author intended.
- Contractors are liable for hidden defects that appear within 10 years of acceptance on completion (paragraph (3)).
- After those 10 years, they are liable for the whole life of the building for defects in the load-bearing structure caused by failing to follow the design or the execution standards in force when it was built (same paragraph).
The warranty period in the contract is something else: it is the window in which the contractor fixes hidden defects that appear, with minimum durations by consequence class (article 531 paragraphs (6) and (7) of the Urbanism Code); if the contract is silent, the legal minimum applies automatically. The durations are on the acceptance page above. What the consequence class is we explained in consequence class and who checks.
For apparent defects, the limitation period for a claim starts at final acceptance, or when the deadline given to the contractor in the final acceptance record to fix them expires (article 1,880 paragraph (1)).
When your choices clear them
Article 1,879 splits liability between those who worked on the house. The contractor is cleared only if it proves the defects come from flaws in the reports or plans of the architect or engineer chosen by the owner (paragraph (3)). Each of them can be cleared by proving the defects come from decisions you imposed in choosing the ground, the materials, the subcontractors, the experts or the building methods, with one limit: this does not apply if the defects could have been foreseen during the works and were not notified to you (paragraph (4)).
In practice: a material you picked against the contractor’s written advice is your risk, and the written advice is what makes the difference.
If you change builder halfway
Article 451 of the Urbanism Code has a rule the pre-Code templates do not have. The new contractor takes on full responsibility only once the contract with the one replaced has ended, and the takeover is made in writing (paragraphs (4) and (5)). The contractor replaced answers for what it did and signed before it was replaced, for hidden defects caused by its own errors, and is cleared if its work loses the intended performance because whoever replaced it changed the solution (paragraph (6)).
So: termination first, written takeover second, and a record of progress at handover, so that it is clear who did what.
What is worth having in the contract
| Clause | Why | Basis |
|---|---|---|
| The subject, with a reference to the building permit | Places the contract under the construction rules | 1,874 |
| Price type and what happens on changes | A fixed price stays fixed unless you write otherwise | 1,865, 1,867 |
| Stage payments tied to stage acceptance | Otherwise you pay everything on acceptance, and unpaid workers have a direct claim | 1,864, 1,856 |
| Procedure for works that get covered up | Notice period and form | 1,876 para. (3) |
| List of subcontractors or your consent to them | Liability stays with the contractor, but it helps to know who is working | 1,852 |
| Warranty period, at least the legal minimum | The contract cannot go below the law | 531 para. (6)-(7) Urbanism Code (and 451 para. (2) for liability) |
| Acceptance on completion and final acceptance | When risk passes and the periods start | 1,878, 1,880 |
The table is a reading of the law, not a contract template.
This article is analysis, not legal advice. The provisions cited are from the Civil Code (Law 287/2009, republished) and from Legea 169/2026, published in Monitorul Oficial no. 661 of 10 August 2026. Romanian legal terms are kept in the original where there is no exact English equivalent. Check your own situation with the issuing authority, and a specific contract with a lawyer.