Urbanism certificate for splitting or merging land

Cadastral operations have their own urbanism certificate, issued within 10 working days. Without it, or against its terms, the deeds are absolutely void.

Citește în română

People ask for a certificat de urbanism in order to build, and assume that splitting a plot means going straight to the notary and the cadastre. The Cod puts one document in between, and the penalty for skipping it is not a fine.

It is a distinct type of certificate

Article 253 paragraph (3) classifies urbanism certificates by the purpose of the request, and letter b) is the certificate for operațiuni cadastrale. It is not a box ticked on the same form used for building. It is a type of its own, with its own regime.

Article 256 paragraph (1) defines it: the individual administrative act by which the local authority makes known the conditions required for operations of dezlipire, alipire, or registering rights of way, and for evidențieri and reevidențieri of properties in the cartea funciară, measured against the technical regime set by approved spatial planning and urbanism documentation.

The list covers more than cutting one plot into two. Merging, a right of way, and registration in the land book all fall into the same category.

The penalty is absolute nullity

Paragraph (2) is the sentence to remember. The operations in paragraph (1), and the legal deeds connected to them, carried out without the certificate or without observing the conditions it imposes, are struck with absolute nullity.

Two situations, not one. The missing certificate is the first. The second is the certificate obtained and then not followed, which happens more often: the certificate sets a condition, the operation is done differently, and the deed is just as void.

The code says only that the sanction is absolute nullity. How that works comes from general civil law, not from this code: it is not cured by the passage of time the way other defects are. And it reaches the connected legal deed, meaning the sale or the partition built on top of the operation. That is why this step is not skipped even when everyone at the table agrees.

The code does make two exceptions. Paragraph (10) exempts engineering works for national transport infrastructure, and paragraph (11) operations for special-purpose zones of the defence, public order and national security institutions.

What you file for a subdivision

The request has its own form, F_CU_02, from Ordinul nr. 975/2026; the whole set, by procedure, is in the Codul urbanismului forms. You tick the operation, subdivision (dezmembrare, dezlipire), merger (comasare, alipire), right of way, registration or re-registration, describe it briefly and attach:

  • the cadastral documentation;
  • a plan with the proposed subdivision or merger;
  • a current land registry extract;
  • the location plan, in the Stereo 70 system;
  • the power of attorney, if you are not filing yourself.

The certificate that comes back is form F_CU_06. At point 7, the mandatory conditions, it has three options: the operation can go ahead on the attached cadastral documentation, stamped as not to be changed; it can go ahead subject to drawing up or approving a PUZ; or it cannot go ahead, with the reasons written. In our reading, in the first option the stamped documentation is itself the certificate’s condition, so a subdivision made on a different plan falls into the second nullity case in article 256 paragraph (2), a certificate obtained and not complied with.

The deadline is short

Paragraph (4) gives at most ten working days from the date the request is registered. For comparison, the usual rhythms of a building file are in the order of steps.

Ten working days means a cadastral operation does not need months of planning, but it will not be sorted on the day you need it at the notary either.

Form and signature

Paragraph (3) lets the applicant choose: the certificate is issued and communicated in written or digital format, according to the option expressed in the standard request form. Paragraph (5) says who signs it, by hand or electronically: the president of the county council or the mayor, as the case may be, together with the secretary and the chief architect or the person responsible for urbanism in the issuing authority’s own staff. Responsibility for issuing it rests with the signatories.

Where it meets a building file

An ordinary urbanism certificate does not give you the right to carry out works. Article 253 paragraph (2) says so directly, and it holds for every type: the certificate is issued to anyone interested in knowing the regime of a property, and it does not confer the right to build or demolish.

If the land you intend to build on is going to be split or merged, order matters. The cadastral operation is done on the basis of its own certificate, and the permit file starts from the resulting land-book situation. What right over the land the permit then requires is covered in a permit on rented land, and the certificate types and their contents are on the page about the urbanism certificate.

The order, not the document

The deadline is short, but the certificate is not automatically positive. Paragraph (8) also allows a reasoned negative certificate, rejection of an incomplete request, or a requirement to prepare a PUZ where the land is split into more than 3 parcels. What costs people most often, though, is the order: first the certificate for cadastral operations, then the operation and the deeds resting on it. The other way round, you do not have a file with something missing, you have deeds struck with absolute nullity.

If a split leaves part of the land with no street access, the access rules are in the right of way and the permit.


This article is analysis, not legal advice. Provisions are cited from Legea 169/2026, published in Monitorul Oficial no. 661 of 10 August 2026. Check your own situation with the issuing authority. Romanian legal terms are kept in the original, because the Romanian text is the one that governs.

AutoRize Team

The AutoRize team

We write about construction permitting in Romania: what has changed, what it means for your file and what to do now.

Your certificat de urbanism file, in 30 seconds

AutoRize generates the application, the memoriu de prezentare and the opis for the certificat de urbanism, matched to local planning rules.

Get started