A room built onto the house is an extension, and an extension almost always needs a permit. The 25 sq m exception, the land book and regularisation, by article.

Citește în română

On an old house, an extension looks like the simplest job: same foundations, same walls, one more room. At the permit stage it is one of the heaviest, because it combines the rules for a new building with the rules for an existing one. We take them in the order you meet them.

Romanian terms are kept in the original: the notificare is the simplified procedure that replaces the building permit for a short list of works.

What an extension is, for the law

Article 372 paragraph (2) of Legea 169/2026 separates two jobs we usually call by the same name:

WorkThe Code’s definitionLetter
ExtensionIncreases the existing building’s footprint and volumed)
Adding storeysIncreases volume with extra storeys, full or partial, keeping the existing building in fulle)

If the new storey does not keep everything that exists, it is no longer adding a storey but partial demolition followed by rebuilding. We explained the consequence in what counts as an intervention. For an attic turned into rooms the rules are separate, in converting the attic.

The notificare covers very little

The list of works on existing buildings that go through a notificare (article 294 paragraph (2) letter b)) has two points touching extensions. Point (x) covers extending rooms to fit bathrooms or plant rooms, of at most 25 sq m, outside protected areas. Point (iv) adds renovating and extending the kitchen and the bathroom, with no maximum area. The list ends with in apartments in collective housing, and the text does not make clear whether that applies to the whole point or only to balconies. For a house, ask the town hall before relying on it. How it applies in a block of flats is in enclosing a balcony.

There is one more route that looks like an extension but is not: letter a) point (i) allows, through a notificare, new buildings outside the dwelling, such as summer kitchens, garages or covered terraces, of at most 50 sq m in total, only in rural areas, inside the intravilan, outside rural localities in metropolitan areas. A separate building in the yard can fit here. A room joined to the house cannot. The thresholds for buildings in the yard are in household outbuildings.

For everything else, including the added living room or bedroom, you need a building permit. What the file contains is on the page about the building permit.

The house must be in the land book

Article 257 paragraph (8) letter a) requires, for the urbanism certificate for horizontal extensions, an up-to-date land book extract with the property registered in the cadastre, and the proposed site plan showing the footprint of the parts to be extended. For other interventions on existing buildings, the same text also accepts a location plan issued by the cadastre office if the property is not registered. For a horizontal extension it does not offer that alternative.

Old houses are often unregistered, or registered with a different area from the real one. If that is your case, it is the first step, before the architect. The steps are in registering the house.

The extension is judged by today’s rules

Article 252 letter a) exempts from a new urban plan the works that keep the use, the built footprint and the volume. An extension changes the last two by definition, so it must fit the urbanism regulation in force: POT, CUT, setbacks from neighbours and from the street. The fact that the rest of the house does not meet them, because it was built under other rules, does not let you carry on the same way. Distances are in how close to a neighbour you can build.

The design has the pieces of a new house plus, where relevant, a survey of the existing building, a technical expert report or technical note, and a diagnostic analysis (article 282 paragraph (1)). And article 370 paragraph (17) allows the building’s original consequence class to be changed, with reasons, for an extension or added storey, which can also change who checks the design; we covered that in the consequence class.

If the extension already exists

Article 301 paragraph (2) allows a regularisation permit for single-family houses of ground floor, or ground floor plus one storey, with a gross floor area of at most 150 sq m, that are not monuments and are not in protected areas, and for outbuildings of at most 150 sq m. If the extension takes the house over the threshold, the general rule no longer helps.

Paragraph (7) opens regularisation to other buildings too, for one year from the Code’s entry into force, with state-control quotas and fees ten times higher (paragraph (8)). Until regularisation, paragraph (11) increases the building tax by 100% from the date the breach is recorded. The timing of that year is in the one-year regularisation window, and the procedure on the page about the regularisation permit.


This article is analysis, not legal advice. The provisions cited are from Legea 169/2026, published in Monitorul Oficial no. 661 of 10 August 2026. Check your own situation with the issuing authority.

AutoRize Team

The AutoRize team

We write about construction permitting in Romania: what has changed, what it means for your file and what to do now.

Your certificat de urbanism file, in 30 seconds

AutoRize generates the application, the memoriu de prezentare and the opis for the certificat de urbanism, matched to local planning rules.

Get started