The Urban Planning Code (Legea 169/2026) does not say what the seismic risk classes mean, and it does not say how an owner finds out the class of their building. It uses the class in three ways that matter when you want to strengthen a house or a block: an urgent-regime permit, fee exemptions and a rule for the technical expert report. The three do not share the same conditions, and anyone who mixes them up ends up believing that every strengthening is fee-exempt or that every class I building gets a permit on the spot.
Class I and public danger: what each one triggers
| What | Condition | Effect | Where it says so |
|---|---|---|---|
| Urgent-regime permit for strengthening | Building classed in seismic risk class I, by technical expert report or justifying technical note, and presenting public danger | Permitted on an urgent basis, with no fee charged | art. 283 para. (3) |
| Exemption from the 0.5% quota to the State Inspectorate in Construction (I.S.C.) | Strengthening works on residential buildings classed in class I | The 0.5% quota is not paid | art. 352 para. (1) |
| Exemption from permit fees | First-urgency intervention works to make safe a construction that presents public danger | No permit fee | art. 313 para. (3) |
| Exemption from the 0.1% state-control quota | The same first-urgency works on a construction with public danger | The 0.1% quota is not paid | art. 143 para. (4) |
| General technical expert report | Intervention that changes the structural system or the overall behaviour | At 0.15 g or more, the report sets the class in the proposed situation | annex 2, pt. 1.4.4 lit. c) |
| Class after strengthening | Public buildings or consequence class 4 | Must reach class RsIV | annex 2, pt. 1.4.4 lit. c) |
The urgent procedure: what it asks and what it permits
The urgent procedure is reserved, under article 283 paragraph (1), for buildings and infrastructure that present a public danger that seriously affects the safety of the population, established by a technical expert report, a justifying technical note of an attested technical expert, or a calamity record. Then the building permit for first-urgency intervention works is issued immediately. Paragraph (2) says what the works are: mainly propping of damaged structural or non-structural elements, partial demolition and strengthening of the load-bearing structure, mandatory in cases of damage, technical accidents, calamities or other exceptional events. Paragraph (3) adds the strengthening of class I seismic risk buildings that present public danger, also permitted on an urgent basis and with no fee. Paragraph (4) asks the environmental authorities to give their opinion on an urgent basis.
For listed monuments and for constructions with architectural or historic value set by urban planning documents, the permit is issued on the written agreement of the Ministry of Culture or its local departments, within at most 5 working days (paragraphs (5) and (6)); the text adds that once the deadline has passed, the works notified are deemed to have tacit agreement.
Article 372 paragraph (2) letter c) defines first-urgency works as any works needed on existing constructions that present a danger of losing their stability, functionality or unique properties because of degradation caused by natural or man-made factors, and that result in making them safe or in their demolition. Strengthening has its own letter, g): works that bring the construction to the right level of performance for resistance and stability. How the fifteen categories of article 372 paragraph (2) sit next to each other we explained in a change of use counts as an intervention.
The Code does not define public danger and does not say who establishes it besides the expert, the technical note or the calamity record, so there is no list of signs to recognise it by.
The exemptions do not share conditions
A quick reader would think that a class I building escapes every fee. The text says otherwise, in four provisions with different conditions.
Article 283 paragraph (3) requires both conditions at once: class I and public danger. Taken literally, a class I house with no public danger does not enter the urgent procedure. The exemption from the 0.5% quota in article 352 paragraph (1) has a single condition, class I, but only for residential buildings and only for strengthening works. The permit-fee exemption in article 313 paragraph (3) does not mention the class at all: it covers first-urgency works on constructions with public danger, whatever their use. And the exemption from the 0.1% quota in article 143 paragraph (4) has the same condition as the permit-fee exemption, public danger, not class I.
It follows, on our reading, that an ordinary strengthening of a class I house with no public danger does not pay the 0.5% quota, but the permit fee and the 0.1% quota remain, because their exemptions require public danger. The texts do not say this in so many words, and each article also leaves room for other cases set by special laws that we have not analysed.
What the rest of the permit fees look like is on the page about fee calculation, and the two quotas to I.S.C. and to state control are explained in the 2026 ISC levy.
Ordinary strengthening: permit, expert report, design
With no public danger, strengthening follows the route for intervention works. Article 259 paragraph (2) letter b) and paragraph (3) list strengthening among interventions on existing buildings, and paragraph (6) makes the permit mandatory, outside works on notification or with no formality. The notification list does not include strengthening. Indeed, an attic conversion on notification, in article 294 paragraph (2) letter b) point (iii), is allowed only if no measures to strengthen the building are needed.
Article 285 paragraph (2) bases intervention works on technical expert reports by attested experts, and paragraph (1) bans self-build for anything other than maintenance and current repairs. So strengthening is not something you do yourself, but with a contractor and on a verified technical design. The expert report is mandatory, under article 437 paragraph (2) letter a), to substantiate the design of interventions on existing constructions.
Annex 2, the one with the framework content of the design, adds in point 1.4.4 letter c) the rule for seismic zones: when the intervention changes the structural system or the overall behaviour, the expert report is general and, where the ground acceleration is at least 0.15 g, it must set the seismic risk class in the proposed situation. If measures to raise performance are needed, as for buildings in classes RsI and RsII, the expert report recommends the solutions and sets the class after strengthening. For public buildings and those in consequence class 4, the annex requires the building to reach class RsIV after strengthening. How the report is done is in technical expert reports on existing buildings.
What the Code leaves unclear about the class
The Code uses two spellings: class I in articles 283 and 352 and RsI, RsII, RsIV in annex 2. It does not say they coincide and it defines none of the classes. There is no RsIII anywhere, and the plain-numeral spelling never goes beyond class I. The Code does not point to any other act for classification either. Our reading is that class I and RsI are the same thing, but the text does not confirm it.
It does not say how an owner finds the class either. The only route it describes is the expert report: article 283 paragraph (3) speaks of buildings classed by technical expert report or by justifying technical note. The National Register of Constructions will hold the classification in seismic risk classes (article 417 paragraph (5)), and the spatial planning and urbanism (ATU) expertise centres, where they are set up, manage databases on classed buildings (article 134 paragraph (3) letter i)), but no article says when or how each building gets a class. On the register, in the National Register of Constructions.
If the building belongs to a local authority
Article 303 lets local authorities demolish, on a demolition permit and in an urgent regime, constructions owned by the administrative-territorial unit that are in an advanced state of degradation and endanger public safety, other than listed monuments. Private houses are not covered. The phrases public danger and advanced state of degradation appear in the Code, apart from a mention of railway infrastructure (article 374), only in articles 143, 283, 303 (in the title) and 313, and none gives the council a way to demolish a private house merely because it is degraded.
What to do first
The first step is the expert report, not the permit application: it says whether this is ordinary strengthening or public danger, and the procedure, the deadline and the fees depend on that. Without it you cannot know which of the exemptions applies to you.
This article is analysis, not legal advice. The provisions cited are from Legea 169/2026, published in Monitorul Oficial no. 661 of 10 August 2026. Check your own situation with the issuing authority.