In a project financed with EU funds, the moment you must hold the building permit (autorizație de construire) is not set by the Urban Planning Code (Legea 169/2026) but by each call’s applicant guide (ghidul solicitantului). On 27 October 2026 we read four official guides, from two regional programmes and from AFIR. One asks only for the urban planning certificate at contracting, Two allow 9 months, and 10 months including the launch of the works procurement, from signing a contract concluded on a feasibility study or DALI. AFIR ties the permit to the first payment claim that includes works. Where a guide sets a deadline, missing it can end the contract.
What the four guides require
| Call | With the funding application | At contracting | After signing | If the deadline is missed |
|---|---|---|---|---|
| Programul Regional Nord-Est, microenterprises, call 2 (submission 28.09-28.10.2026, now closed) | The general cost estimate (deviz general) on the HG 907/2016 model; no urban planning certificate | Within 15 working days of the notice: a valid urban planning certificate or the permit if already obtained, a land register extract, the designer’s site plan | Neither the guide nor the model contract sets a permit deadline; the works procurement must start within 4 months | Late procurement can be grounds for termination |
| Programul Regional Nord-Est, schools in rural communes (call closed in 2025, guide revised 28.01.2026) | Feasibility study or DALI at most 2 years old, a valid urban planning certificate; at technical design stage, the permit | All approvals required by the certificate, except the ISU (fire) approval; at technical design stage, the permit | Contract signed on a feasibility study or DALI: design tender notice within 3 months; technical design, permit and launch of the works procurement within 10 months in total. Contract signed on a technical design: works tender notice within 3 months | The managing authority can terminate the contract and recover the funding |
| Programul Regional Sud-Vest Oltenia, energy efficiency in public buildings, call 2 (submission 02.10-03.12.2025) | Feasibility study or DALI, urban planning certificate mandatory; with a technical design, the permit as well | Right over the property; the contract may be signed with a resolutory clause of at most one year | Contract signed on a feasibility study or DALI: technical design and permit within 9 months | Without the technical design on time, the authority may terminate the contract unilaterally |
| AFIR, intervention DR-12, young farmers (session 06.10-02.12.2026) | Feasibility study on HG 907/2016 and documents proving the right to obtain the permit; the guide does not list the urban planning certificate | The technical design, within at most 6 months of the selection notice and before signing | The permit, with the first payment instalment that claims works; that instalment is due within 12 months, extendable by 6 months with a 0.1% penalty | Termination of the contract and recovery of the advance |
With the funding application
For construction works, a funding application usually rests on a feasibility study (SF) or an intervention approval documentation (DALI) and on an urban planning certificate issued for permitting the works in the project. In the two calls for public beneficiaries we read (the Nord-Est schools and the Sud-Vest Oltenia public buildings), a certificate that has expired on the submission date gets the application rejected as administratively non-compliant. In the Nord-Est microenterprise call the certificate comes only at contracting, and AFIR’s DR-12 guide does not list it among the documents.
For investments financed from public funds, the feasibility study is required by regulation too, not only by the guide: by HG 907/2016 and, for projects under the Code’s stages, by article 492(2), which makes it mandatory for any investment financed wholly or partly from public funds. The exceptions in paragraph (3) are emergencies, routine repairs and works done on notification or with no formality. Whether paragraph (2) also reaches a private beneficiary of an EU grant, the Code does not say explicitly; ask the managing authority.
If the permit already exists, it shortens the file. For cohesion-policy programmes such as the regional ones, OUG 23/2023 says in article 6(6) that if you submit a valid building permit with the application, you are not asked for the approvals, agreements and property documents it was issued on. The ordinance covers cohesion-policy funds, so it does not reach AFIR’s interventions, which are financed from the rural development fund.
The deadline after signing
This is where the calls differ most. In Sud-Vest Oltenia, for a contract signed on a feasibility study or DALI, the technical design and the permit are due within 9 months of signing. For the rural schools in Nord-Est, the guide version of 28 January 2026 replaced the 9 months for technical design and permit with a total limit of 10 months, which also covers launching the works procurement, again for contracts signed on a feasibility study or DALI. The microenterprise guide from the same region sets no deadline for the permit, but requires the works procurement to start within 4 months of signing.
The one-year resolutory clause often mentioned for the regional programmes is about the right over the land or building, not about the permit (OUG 23/2023, article 6(11)). Permit deadlines come from the guide and the contract, so that is where to read them, for your call.
AFIR orders the steps differently. DR-12 asks for the technical design before the contract is signed, and for the permit only with the first payment claim that includes works. HG 907/2016, however, says in article 5(4) that the technical design for execution is drawn up after the permit is issued, and the Code says the same in article 264(5). The guide does not explain how the two fit together. Our reading: for a DR-12 investment with construction, plan the permit within the 6 months before the contract, so the technical design handed to AFIR is the one developed from the permitted documentation.
HG 907 or the Code: which rules you work under
Publicly funded projects are designed in the phases of HG 907/2016: feasibility study or DALI, then the permit documentation, then the technical design for execution. The Code has its own life cycle of the construction investment project, in stages, in book 2 part IV. Article 577(1) takes four categories of HG 907 projects out of those stages: those with works in progress when the Code entered into force (letter a), those whose SF, DALI or technical design procurement had started or whose documentation had been accepted or submitted for approval (letter b), those “pentru care a fost aprobată finanțarea” (for which the funding has been approved, letter c), and those whose documentation, accepted before the Code, needs updating (letter d). Paragraph (2) applies to them the legislation in force on the date of the situation concerned. Letter c) sets no date. Our reading, which the text does not settle: a project whose funding has been approved, even after 25 August, stays on HG 907, not on the Code’s stages. Confirm with the managing authority.
The difference shows in the name of the permit documentation. HG 907 still calls it D.T.A.C. (in article 1 and annex 9), a name introduced by HG 1116/2023 in place of the earlier P.A.C., and on legislatie.just.ro the decision had no amendment recorded after 2023 as of 27.10.2026. The Code calls it the project for building authorisation, PAC (article 503(4) and (8)), and never uses the term DTAC. What changes in practice for documentation started as a DTAC is covered in your documentation says DTAC.
Several guides still cite the old law. The Sud-Vest Oltenia guide refers to Legea 50/1991, and so does the regulations annex of the Nord-Est microenterprise call, published with the August 2026 guide. Legea 50/1991 has been repealed since 25 August 2026, and article 583(3) of the Code says references to repealed provisions are read as references to the Code. Of the four guides, only DR-12 cites Legea 169/2026.
Approvals, with priority
Article 316(1) of the Code lists the obligations of the bodies that issue approvals (avize); paragraph (2) exempts the acts of the environmental authority. Letter j) requires the issuers to review and approve, with priority and as a matter of urgency, documentation for investments financed from the PNRR or from other EU funds. The Code gives no shorter deadline and no sanction for this priority. The usual issuing deadlines remain those in article 269, which letter b) refers to.
Letter i) adds that approvals for public works projects are issued without fees or review charges. Annex 1 of the Code defines public works by financing from public funds or by a beneficiary that is a public authority or institution. For a city hall or a school the exemption is clear; whether it also applies to a private beneficiary with EU funds is a question for the issuer. Which approvals the urban planning certificate requires and where to get them is explained on the page about approvals for the building permit.
It is worth stating plainly in the approval request that the investment is financed with EU funds, and under which call. Otherwise the issuer has no way of knowing the file falls under letter j). How long approvals stay valid once obtained, on a project that runs for years, is covered in avize last until recepție.
What AutoRize does in the permit file
AutoRize prepares the administrative part of the permit file. It reads the urban planning certificate and the land register extract and takes the project data from them. It lists the approvals the certificate requires, with the pieces and number of copies for each, and generates the approval requests. It fills in the certificate application F_CU_04, the permit application F_A_01 with its technical annex, the memoriu and the document index (opis), in Word, so you can edit them before filing.
The technical part of the PAC, the feasibility study, the cost estimate and the funding application stay with the designer and the funding consultant. For a call with a 9- or 10-month deadline, the data from the certificate is written once and reaches every application unchanged, and the list of approvals comes straight from the certificate. What the app does for a design practice is described on the page for architects. Which calls your own practice can apply to, with CAEN code 7111, is collected in EU funds for architects.
To check in your call’s guide
Before you plan the permit, look for five things in the guide. First, the documentation phase required at submission (SF, DALI or technical design) and how old it may be. Then when the urban planning certificate is due, at submission or at contracting, and whether it must be valid on both dates. For approvals, how many you need before the contract and which are exempted, like the ISU approval for the Nord-Est schools. For the permit deadline, from which date it runs, what else it includes (technical design, launching procurement) and whether it can be extended. And if the guide still refers to Legea 50/1991, ask the managing authority how it applies the Code to your call.
Guides and acts, in the versions of 27.10.2026: the microenterprise call 2 guide on regionordest.ro, the rural schools guide on regionordest.ro, the energy efficiency call 2 guide on pr2021-2027.adroltenia.ro, the DR-12 guide and model contract on afir.ro, OUG 23/2023 and HG 907/2016.
This article is an analysis, not legal advice. The provisions cited are from Legea 169/2026, published in Monitorul Oficial no. 661 of 10 August 2026, from HG 907/2016 as consolidated on 23 November 2023, from OUG 23/2023 and from the guides of the calls named, in the versions read on 27 October 2026. Guides change through corrigenda, so check the version in force for your call. Romanian legal terms are kept in the original where no exact English equivalent exists. Check your own situation with the issuing authority.