Annulling a building permit: who can, and by when

Annulling a neighbour's building permit: who can ask, the 30-day complaint, the 6-month action and the two dates on which the Code treats you as informed.

Citește în română

Your neighbour has been granted a building permit and you think it breaks the law. The Urban Planning Code (Legea 169/2026) leaves the annulment of a building permit issued in breach of the law to the administrative court and gives any person the right to bring the case. For conditions and deadlines, the Code refers to Legea 554/2004 on administrative litigation: a prior complaint within 30 days of learning of the permit, then an action within 6 months of the reply. The Code’s own contribution is different: it sets the date on which the content of the permit counts as brought to the public’s attention. The Code does not say expressly that the deadlines run from there for anyone who did not receive the permit, and article 314 points to two different moments for that date.

Each step and its deadline

StepDeadlineRuns fromWhere it says so
Prior complaint to the authority that issued the permit30 days; for good reasons, at most 6 monthsThe date you learned, by any means, of the content of the actLegea 554/2004, art. 7(3)
Action for annulment before the administrative court6 monthsThe reply to the complaint, the refusal to deal with it, or the expiry of the deadline for dealing with itLegea 554/2004, art. 11(1)
The action, where the complaint is no longer mandatory (the act can no longer be revoked)6 monthsThe date you learned of the content of the actLegea 554/2004, art. 11(1)(d¹), art. 7(5)
The action, for good reasonsAt most 1 yearThe date you learned of the act, as the case may beLegea 554/2004, art. 11(2)
Request to suspend the permitAfter the prior complaint or, for an act that can no longer be revoked, within 30 days of learning of it; the annulment action must follow within 60 days at mostThe date the suspension request is filedLegea 554/2004, art. 14(1); Legea 169/2026, art. 362
Date on which the public counts as informedThe last publicity stepTwo paragraphs point to different momentsLegea 169/2026, art. 314(7)-(9)

Article 7(3) classes as limitation periods the third party’s 6-month deadline for the complaint and the 6 months that paragraph (1) gives the addressee of the act; it says nothing about the 30 days. For the action, the 6 months are a limitation period and the one year in paragraph (2) is a strict time bar (decădere, article 11(5)).

Who can ask for annulment

Article 360(1) of the Code gives any person the right to bring a case before the administrative court, but in accordance with Legea 554/2004. Paragraph (2) adds that building, demolition, modification or regularisation permits issued in breach of the law can be annulled by those courts.

Legea 554/2004 narrows that any person. Article 1(1) opens the court to a person who considers themselves harmed in a right or a legitimate interest, and the legitimate interest can be private or public. A neighbour whose light, access or privacy the building takes away can argue a private interest. For associations, the High Court of Cassation and Justice held in appeal in the interest of the law no. 8/2020 that a public interest must be invoked as secondary to a private interest directly linked to the purpose in their statutes. Anyone who shows no connection with the building faces real difficulties in court.

On what grounds

The Code gives no list of grounds for annulment, but it shows what a wrongly issued permit is. Article 357(1)(s) sanctions issuing a building or demolition permit in three situations. First: without a right that entitles the applicant to ask for the permit, under article 248. Second: without, or in breach of, the approved urban planning documentation. Third: on documentation that is incomplete, does not match the urban planning certificate or the Civil Code, lacks the required approvals or has not been checked as the law requires. These are contraventions of the issuer, not grounds for annulment written as such, but they describe exactly the situations in which a permit is issued in breach of the law.

What to check in practice: the indicators in the permit against the urban plan, the setbacks from your boundary, the height, the approvals required by the urban planning certificate. Some of them must be public, as below.

When you count as informed

For the person who receives the act, the deadline runs from notification. As a neighbour you receive nothing, so Legea 554/2004 counts from the date you learned, by any means, of the content of the act. The Code has its own rule for building permits, in article 314.

Within 30 days of issue at most, the authority makes the information about the permit available to the public: at its offices, by posting it or on request, and on its website or on the digital platform that issues the permits (paragraph (2)). The information includes the permit’s number and date, the description of the project, the plot occupancy percentage (P.O.T.) and the land use coefficient (C.U.T.), the setbacks from the boundaries, the areas, the height regime, the site plan and all the facades (paragraph (5)). Separately, after receiving the permit and before starting work, the beneficiary must note its number, date and title in the land register, publish them in a widely circulated newspaper and put up the project identification panel on site (paragraph (7)). The newspaper publication is the notice that so many websites sell.

Paragraph (8) says the public counts as informed on the date of the last publicity step provided in paragraph (2), that is, the ones carried out by the authority. Paragraph (9) refers to the same date as set under paragraph (7), that is, after the beneficiary’s formalities. The text therefore points to two different moments, and the Code does not say which prevails. The same paragraph (9) lets you ask to study, at the authority’s offices, the information in paragraph (5), the items listed above, from the permit number to the site plan and facades, and the other public documents. In the August text the reference was to paragraph (4), the one on permits for special-character buildings, which are not made public; the Rectificare published on 14 October 2026 corrected it.

Our reading, in practice: if you want to challenge the permit, count the deadlines from the earliest of the dates and from any moment you actually learned of it, for example when you saw the panel. If you hold the permit, do not treat it as safe until the deadlines counted from the latest date have passed. For permits issued before the Code came into force, the beneficiary’s formalities can also be done after work starts (paragraph (7), last sentence). Where to find the lists the city hall must publish is in the public list of building permits.

The prior complaint, then the court

The first step is the prior complaint: you ask the authority that issued the permit, or its hierarchical superior if there is one, to revoke the act in whole or in part. For a third party the deadline is 30 days from learning of the act, and for good reasons the complaint can be made later, but not beyond 6 months (article 7(3) of Legea 554/2004).

The complaint is not mandatory, among other cases, against acts that can no longer be revoked because they have entered civil circulation and produced legal effects (article 7(5)). The law does not say when a building permit reaches that point, for example after work has started. Our advice: a complaint made in time costs you nothing, while leaving it out, if the court considers it mandatory, can cost you the case. Where the complaint is no longer mandatory, the action is brought within 6 months of the date you learned of the content of the act (article 11(1)(d¹)).

The action for annulment is brought within 6 months, counted from the reply to the complaint, from the refusal to deal with it, or from the expiry of the deadline by which it had to be dealt with (article 11(1)). For good reasons it can be brought later, but no later than one year (paragraph (2)).

Suspension, if work has started

The annulment case takes time, and the building goes up in the meantime. Article 362(1) of the Code sends suspension to articles 14 and 15 of Legea 554/2004. Under article 14(1), suspension is requested in well-justified cases and to prevent imminent damage, after you have referred the matter to the authority by complaint or, for an act that can no longer be revoked, within 30 days of learning of its content. If you do not bring the annulment action within 60 days of the suspension request, the request is rejected, and a suspension already ordered ends by law.

The Code speeds the case up here. Once the court has suspended the permit, hearings in the annulment case are set at intervals of no more than 15 calendar days (article 362(2)). And urban planning disputes are heard promptly by specialised panels (article 365(1)). Until those are set up, the existing administrative litigation sections hear them (paragraph (2)).

If the permit is annulled

Annulment does not automatically bring down what has been built. Article 364 lets the court, at the permit holder’s request, keep the building if it complies with the law and the planning rules and with the fundamental quality requirements, based on a technical expert report.

We discussed how article 364 applies in the annulled permit and the house already built.

If the works have no permit at all, there is nothing to annul. The route then is an inspection by the city hall or the I.S.C., described in reporting a building put up without a permit. What a building permit contains and how it is obtained is on the page about the building permit.

The timeline, briefly

  1. Note the date you learned of the permit and how: panel, notice, the city hall’s list.
  2. Ask the city hall for the permit and its public annexes, to see what was approved.
  3. File the prior complaint within 30 days of that date.
  4. If work is moving ahead, ask for suspension and bring the action within 60 days of the suspension request at most.
  5. Bring the annulment action within 6 months of the reply, or of the expiry of the deadline for one, or of the date you learned of the permit if the complaint was no longer mandatory.

This article is an analysis, not legal advice. The provisions cited are from Legea 169/2026, published in Monitorul Oficial no. 661 of 10 August 2026, as rectified in Monitorul Oficial no. 862 of 14 October 2026, and from Legea 554/2004 on administrative litigation, in the consolidated form on legislatie.just.ro. Romanian legal terms are kept in the original where no exact English equivalent exists. Check your own situation with the issuing authority.

AutoRize Team

The AutoRize team

We write about construction permitting in Romania: what has changed, what it means for your file and what to do now.

Your certificat de urbanism file, in 30 seconds

AutoRize generates the application, the memoriu de prezentare and the opis for the certificat de urbanism, matched to local planning rules.

Get started