Skip to main content

Permit avize: the fixed tariffs and where to find the rest

Electricity location aviz: 95 lei before VAT on a coexistence sheet. Land register extract for information and cadastral extract: free for the owner.

Citește în română

A few items in a permit file have a tariff set nationally. The location approval (aviz de amplasament) from the electricity network operator has an issuing tariff of 95 lei before VAT for a building, on a coexistence sheet, and the land register extract for information and the cadastral plan extract are free when the owner asks for them. For the other avize we found no tariff set by a national act; the amount is set by the issuer. The law does not require the issuer to publish the amount, but the method by which it is calculated, and that obligation is written down, together with where it gets published.

What the nationally priced items cost

What you pay forWho collectsTariffWhere it is written
Land register extract for information (extras de carte funciară pentru informare)the cadastre office20 lei requested online, 25 lei at the counter; free when the owner asksANCPI Order 16/2019, consolidated form of 8 March 2026, annex, code 2.7.2; art. 8(1)(s)
Cadastral plan extract (extras din planul cadastral)the cadastre office15 lei; free on the same termsannex, code 2.7.7
Location approval from the electricity distribution operator, for a buildingthe distribution operatorissuing tariff, before VAT: 95 lei on the basis of a coexistence sheet, 29 lei on the basis of a coexistence studyANRE Order 114/2014, consolidated form of 1 September 2017 (annex replaced by ANRE Order 63/2017)
The same approval for an individual gas, water or sewer connection, or a network under 1 kmthe distribution operatorissuing tariff, before VAT: 63 lei (sheet), 19 lei (study)the same annex
Environmental procedure: initial evaluation, then the screening stagethe environmental protection agency100 lei, then 400 lei, before VATOrder 1108/2007, consolidated form of 6 January 2022

The exemption is in article 8(1)(s) and covers only codes 2.7.2 and 2.7.7; the land register extract for authentication, which notaries ask for, costs 40 lei. The information extracts are free when the owner asks for them, and when the city hall or county council asks on the owner’s behalf, to issue administrative acts or carry out specific activities, for properties within its area. The text does not say clearly whether those last conditions also apply to a request made by the owner; our reading is that they attach to the request made through the city hall. Free online delivery has applied, under the same text, since 2 June 2025.

The Code asks for these extracts in two places. For the permit, article 262(1)(b) asks for the cadastral plan extract and the land register extract, each no older than 30 days. For the urban planning certificate, article 257(8)(a) asks, for new buildings, landscaping works and horizontal extensions, for an up-to-date land register extract, and letter c) of the same paragraph says the city hall obtains the property data itself, online, through the cadastre application’s interface and the services ANCPI makes available free of charge.

What a house does not pay for at all

Two documents are not required for a single-family home. The public health opinion is not needed for new houses or for any work on existing ones (article 267(2)(a)), except where the law expressly requires a health impact study. The environmental authority’s act is not needed for the same works unless they are in protected natural areas or nature reserves (article 268(2)(a)).

So the environmental tariffs in the table usually concern projects other than a house: outbuildings for animals, commercial buildings, works in protected areas.

The other avize: the tariff comes from the issuer

For the other avize in the urban planning certificate (water and sewerage, gas, waste collection, telephone) we found no tariff set by a national act; the amount is set by the issuer. Article 308(1) says so expressly for avize obtained through the single-approval commission (comisia de acord unic): the amounts are set by the issuers and calculated under the specific legal rules of each field. For private investment works, article 316(1)(a), explained below, requires each issuer to publish the calculation method, and you work out the amount from it before you file.

The list of avize the certificate can ask for is on the page about the avize for a building permit. How the single-approval commission works is in the comisia de acord unic in practice, and how all the permit’s costs add up, layer by layer, in what a permit’s cost is made of.

What must be on the website before you file

Article 316 paragraph (1) letter a) requires the institutions and economic operators empowered by law to issue avize or acorduri to establish three things and make them available to the public and to the competent public authorities: the framework content of the specific documentation, the list of other documents and specific conditions required, and the method of final calculation of the taxes or tariffs for private investment works.

Where it is published is not left open. The text requires the issuer’s own website and display at its premises.

In practice, if you cannot find on the issuer’s site how the tariff is calculated, that absence is not a local quirk. It is an unmet obligation, and asking to be told the calculation method rests on a basis you can name.

One request for completions, within five working days

Letter d) says the issuer sends you, in writing or by email where you have declared an address, once only and within at most 5 working days of receiving the documentation, notice of any completions needed.

Paragraph (4) closes the gap: for avize that do not require analysis in a commission, no request for completion after the 5 working days is permitted.

So completions do not arrive in waves. If an issuer comes back a second time, after five days, on an aviz that does not go through a commission, that return has no cover in the text. For avize analysed in a commission, letter d) also points to other deadlines (to article 269 paragraphs (4) and (10); in the August text the reference wrongly pointed to article 279, and the Rectificare published on 14 October 2026 corrected it), so there the five days are not the only window.

What it is not allowed to cost you

Letter i) prohibits charging analysis fees, consultancy fees or anything similar for public works projects, both new construction and interventions on existing buildings. This is an exemption by regime, not a general one: it concerns public works.

Letter n) adds a prohibition that runs across the whole list: the issuer cannot condition the issue of its aviz on first obtaining other avize or acorduri. That chain, where each issuer asks you for another one’s paper, is not an order imposed by law.

The rest of the list, briefly

Letter b) refers the issuing deadlines to article 269, except for avize on technical and utility networks needed at the technical-economic documentation stage. Letter f) requires applications to be filed and avize issued digitally. Letter g) requires the file to reach the commission agenda AND be analysed in commission within at most 30 days of submission, where the law requires a commission, and letter h) requires the beneficiary and the designers to be told the date of the sitting, whether or not they have the right to attend. Letter m) prohibits changing the case officer partway, with named exceptions: leaving the structure, leave, incapacity for work, disciplinary investigation.

Paragraph (3) sets its own deadlines for cultural heritage: 30 working days for buildings. Paragraph (2) takes environmental regulatory acts out of the article; they follow their own legislation.

How this connects to money

None of the obligations above is a discount. They are something else: they make the cost predictable before you file, and they stop the costs that come from repetition, meaning successive completions and avize demanded in a chain.

The permit fees themselves, which are a different category from issuers’ tariffs, are explained on the page about calculating the taxes.

What to check first

Before filing with an issuer, look for its website and see whether the calculation method is actually there. If it is not, you have a concrete basis on which to ask to be told it; if it is, you know the bill in advance.

What happens when the answer deadline passes with no answer is in tacit approval shortens something.


This article is analysis, not legal advice. The tariffs cited are from ANCPI Order 16/2019 (consolidated form of 8 March 2026), ANRE Order 114/2014 (consolidated form of 1 September 2017, with its annex replaced by ANRE Order 63/2017) and Order 1108/2007 (consolidated form of 6 January 2022), each the latest form on 1 November 2026. The Code’s provisions are from Legea 169/2026, published in Monitorul Oficial no. 661 of 10 August 2026, as rectified in Monitorul Oficial no. 862 of 14 October 2026. Check your own situation with the issuing authority. Romanian legal terms are kept in the original, because the Romanian text is the one that governs.

AutoRize Team

The AutoRize team

We write about construction permitting in Romania: what has changed, what it means for your file and what to do now.

Your certificat de urbanism file, in 30 seconds

AutoRize generates the application, the memoriu de prezentare and the opis for the certificat de urbanism, matched to local planning rules.

Get started