The building permit: steps, documents, cost and deadline
The building permit (autorizație de construire, also called autorizație de construcție) is the document issued by the town hall that allows you to carry out the works (Codul urbanismului, art. 259). You get it in order: the certificat de urbanism, the PAC technical project, the approvals obtained on its basis, then you file the dossier and the town hall issues the permit within 30 days.
Check which rules apply to you
The urbanism code applies from 25 August 2026. If you already have an urbanism certificate issued before that date, the approvals it requires follow the rules in force when it was issued.
Your application will follow the new rules (CATUC), in force from 25 August 2026.
This result is indicative only. The exact rules for your file are determined by the issuing town hall.
In short: the town hall issues the permit within 30 calendar days of the complete file being submitted, or within 7 working days under the urgent procedure. The base fee is 0.5% of the value of the works for a residential building or an annex and 1% for other constructions, and the local council can add additional rates of up to 100% (Codul fiscal, art. 489 paras. 1-2). The permit is valid for 3 years, within which you must start the works.
The steps, in order
- The certificat de urbanism: the first step. It shows what may be built on the plot and which approvals you need; it is issued within 15 working days.
- The project for authorising construction (PAC), formerly DTAC, prepared and signed by an architect and engineers with signing rights.
- The approvals and agreements required by the certificate, obtained on the basis of the PAC (art. 257 para. 3), directly or, if you opt for it, through the Comisia de acord unic (art. 269 para. 1).
- The permit request, on form F_A_01, filed at the town hall together with the complete file, on paper or digitally (art. 270).
- Issue of the permit, within 30 calendar days of filing the complete file (art. 273 para. 1). If the file is incomplete, the town hall notifies you within 10 working days of registration and gives you up to 3 months to complete it (art. 271).
- Starting the works: you notify the town hall and the State Construction Inspectorate before you start, and from then on the validity extends over the whole execution period (art. 309 para. 2). What to notify and when: the start and completion notices.
- Finally, the acceptance on completion of the works.
What documents you need
You file the dossier once you have the certificat de urbanism and the approvals it requires. It includes:
- The request for issuing the permit (standard form set by ministerial order).
- Extract of the cadastral plan and extract of the land register (carte funciară), both updated, no older than 30 days.
- Proof that the project is registered with the Romanian Order of Architects (for buildings).
- The project for authorising construction (PAC): the documentation previously called DTAC.
- Complementary documentation for obtaining the avize through the Single Approval Commission (Comisia de acord unic), if applicable.
- The environmental authority's point of view or administrative act, and the environmental agreement, if applicable.
- The other avize and agreements required by the certificat de urbanism.
- The technical expert report on the impact on neighbouring properties, if applicable.
- The general cost estimate (deviz general), the execution period and the value of the investment.
- The project for the road administrator's agreement or permit, for works on public land, if applicable.
- The project verification reports, drawn up by certified technical verifiers, for the applicable fundamental requirements.
- A sworn statement, if you rely on tacit approval of some avize (art. 269).
How much it costs
The building permit fee is calculated from the authorised value of the works (Codul fiscal, art. 474 paras. 5 and 6):
- 0.5% for a residential building or an annex;
- 1% for other constructions, including the related installations.
The local council can add additional rates of up to 100% (Codul fiscal, art. 489 paras. 1-2). The fee is paid before the permit is issued, on the declared value. After the works are finished you file a statement of the real value and the town hall settles the difference (art. 474 para. 7). For a residential building or an annex, the value cannot be lower than the building's taxable value.
On top of the permit fee come the certificat de urbanism fee and the approval fees, set by each institution. The fee calculator gives a quick estimate, and the cost of a permit, layer by layer shows how all the costs add up.
Issuance deadlines
- General deadline: at most 30 calendar days from submitting the complete documentation.
- Urgent procedure: at your request, the permit is issued within 7 working days. The town hall may charge a special fee for this procedure.
- If you chose to obtain the avize through the Single Approval Commission (Comisia de acord unic), the 30 days are calculated from the date the single approval is issued, not from the initial submission.
If the documentation is incomplete
The town hall notifies you in writing, within at most 10 working days of registration, of all the deficiencies found. The same notification tells you the deadline by which you must complete the dossier, which cannot exceed 3 months. If you do not complete it in time, the town hall returns the dossier to you. You can complete it and file it again while the urbanism certificate is still valid (art. 273 para. 5).
Site organisation
The permit for organising the execution (autorizația de amenajare a organizării execuției) is issued for the provisional preparatory works needed to execute the project: both on the investment land and on spaces temporarily occupied outside it. The documentation was previously called DTOE.
The permit can be requested either together with the building permit or separately, by the general contractor. The documentation includes the memoriu tehnic, the site plan and the road administrator's aviz, or the documentation for occupying public land, if applicable.
Neighbours' agreement
It is required, in notarised form, only when carrying out the works requires safety measures for existing buildings, identified through a technical expert report.
How AutoRize helps
- Generates the certificat de urbanism request (F_CU_04), the permit request (F_A_01), the memoriu, the opis and the aviz requests, in Word and PDF.
- AI auto-fill from the certificat de urbanism or the land registry extract.
- The list of avize shows the issuers, fees and documents required for each aviz; it is configured for Târgu Mureș.
- Official fees and deadlines in one place, with reminders for the important dates.
Frequently asked questions
How long does it take to obtain the building permit?
The law provides for issuance within 30 days of submitting the complete dossier. On top of that comes the time for the certificat de urbanism, the avize and preparing the technical documentation.
How long is the building permit valid?
The building permit is valid for 3 years from issuance, during which you must start the works. This deadline cannot be extended, but it can be suspended once, for at most 12 months. The execution period is extended separately, once, by at most 12 months. After you announce the start of the works, validity automatically extends for the execution period set out in the permit.
Which works can be done without a permit?
The law exempts certain minor works, such as some repairs and finishes that do not change the structure or the architectural appearance. The exact list is in the Codul urbanismului (Legea 169/2026); when in doubt, ask the town hall.
How much does the building permit cost?
The base fee is 0.5% of the authorised value of the works for a residential building or an annex and 1% for other constructions, including installations (Codul fiscal, art. 474 paras. 5 and 6), and the local council can add additional rates of up to 100% (art. 489 paras. 1-2). It is paid before the permit is issued, on the declared value, and settled after the works are finished, on the real value. On top of it come the certificat de urbanism fee and the approval fees.
Does AutoRize replace the architect or designer?
No. The PAC technical documentation is prepared and signed by licensed specialists. AutoRize generates the administrative documents of the dossier and guides you through the process.